Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,570
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0782 # 04 Y:2004 | 04 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,280 | $2,145 | Implemented |
GT0782 # 05 Y:2004 | 05 | 2004 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,625 | $200 | Implemented |
GT0782 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $540 | $450 | Implemented |
GT0782 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $610 | $2,340 | Implemented |
LM0075 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $757 | $175 | Implemented |
LM0075 # 04 Y:2004 | 04 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $156,419 | $6,500 | Implemented |
LM0075 # 06 Y:2004 | 06 | 2004 | INSULATE BARE EQUIPMENT | $309 | $101 | Implemented |
OK0685 # 01 Y:2004 | 01 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $265,308 | $559,374 | Implemented |
OK0685 # 02 Y:2004 | 02 | 2004 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $10,694 | $34,154 | Implemented |
OK0685 # 03 Y:2004 | 03 | 2004 | INSULATE BARE EQUIPMENT | $23,175 | $1,573 | Implemented |
OK0685 # 04 Y:2004 | 04 | 2004 | INSULATE BARE EQUIPMENT | $9,972 | $3,312 | Implemented |
OK0685 # 06 Y:2004 | 06 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,053 | $2,023 | Implemented |
MS0249 # 01 Y:2004 | 01 | 2004 | OPTIMIZE PLANT POWER FACTOR | $54,067 | $26,100 | Implemented |
MS0249 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $19,536 | $250 | Implemented |
MS0249 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,879 | $708 | Implemented |
MS0249 # 11 Y:2004 | 11 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $488 | $820 | Implemented |
SU0185 # 02 Y:2004 | 02 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $19,053 | $0 | Implemented |
SU0185 # 03 Y:2004 | 03 | 2004 | INSTALL OCCUPANCY SENSORS | $345 | $30 | Implemented |
SU0185 # 04 Y:2004 | 04 | 2004 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $8,959 | $92 | Implemented |
SU0185 # 06 Y:2004 | 06 | 2004 | INSTALL OCCUPANCY SENSORS | $9,676 | $30,734 | Implemented |
UM0252 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $47,515 | $40,000 | Implemented |
UM0252 # 03 Y:2004 | 03 | 2004 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $9,272 | $16,000 | Implemented |
UM0252 # 04 Y:2004 | 04 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,381 | $400 | Implemented |
UM0252 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,568 | $3,999 | Implemented |
BD0258 # 01 Y:2004 | 01 | 2004 | INSTALL OCCUPANCY SENSORS | $2,506 | $2,025 | Implemented |