Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
627
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0010 # 04 Y:2024 | 04 | 2024 | INSULATE BARE EQUIPMENT | $9,629 | $1,369 | Implemented |
SJ0010 # 03 Y:2024 | 03 | 2024 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $626 | $0 | Not Implemented |
SJ0010 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $58 | $0 | Implemented |
SJ0010 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $780 | $0 | Implemented |
SJ0007 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $128,947 | $765,487 | Not Implemented |
SJ0007 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,271 | $13,090 | Not Implemented |
SJ0007 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $951 | $495 | Not Implemented |
SJ0007 # 04 Y:2023 | 04 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $192 | $0 | Not Implemented |
SJ0007 # 05 Y:2023 | 05 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,529 | $0 | Not Implemented |
SJ0007 # 06 Y:2023 | 06 | 2023 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $31,866 | $36,311 | Not Implemented |
SJ0007 # 07 Y:2023 | 07 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $47,492 | $0 | Not Implemented |
SJ0007 # 08 Y:2023 | 08 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,635 | $0 | Not Implemented |
CI0020 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $76,570 | $180,000 | n/a |
CI0020 # 03 Y:2023 | 03 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $55,349 | $45,000 | n/a |
CI0020 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,503 | $2,870 | n/a |
CI0020 # 05 Y:2023 | 05 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,187 | $20,000 | n/a |
CI0020 # 06 Y:2023 | 06 | 2023 | USE PHOTOCELL CONTROLS | $1,246 | $750 | n/a |
CI0020 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $92,262 | $487,880 | n/a |
SJ0006 # 08 Y:2023 | 08 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $332 | $1,762 | Not Implemented |
SJ0006 # 07 Y:2023 | 07 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $8,791 | $39,456 | Not Implemented |
SJ0006 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,713 | $4,600 | Not Implemented |
SJ0006 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $132,467 | $665,395 | Not Implemented |
SJ0006 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,014 | $7,324 | Not Implemented |
SJ0006 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $798 | $2,977 | Not Implemented |
SJ0006 # 04 Y:2023 | 04 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,078 | $7,298 | Not Implemented |