Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,415
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0293 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,827 | $320 | Implemented |
MZ0293 # 02 Y:2020 | 02 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,246 | $6,782 | Implemented |
MZ0293 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,924 | $910 | Implemented |
MZ0293 # 04 Y:2020 | 04 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,596 | $4,100 | Not Implemented |
MZ0293 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $63,762 | $88,053 | Implemented |
MZ0293 # 06 Y:2020 | 06 | 2020 | INSTALL OCCUPANCY SENSORS | $230 | $780 | Implemented |
MZ0293 # 07 Y:2020 | 07 | 2020 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $7,010 | $25,500 | Not Implemented |
MZ0293 # 08 Y:2020 | 08 | 2020 | OPTIMIZE PLANT POWER FACTOR | $328,879 | $538,653 | Implemented |
MZ0293 # 09 Y:2020 | 09 | 2020 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,186 | $28,360 | Not Implemented |
AM0806 # 01 Y:2020 | 01 | 2020 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $49,500 | $85,000 | Not Implemented |
AM0806 # 02 Y:2020 | 02 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,025 | $24,685 | Not Implemented |
AM0806 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,300 | $10,600 | Implemented |
AM0806 # 04 Y:2020 | 04 | 2020 | INSULATE BARE EQUIPMENT | $5,470 | $3,350 | Implemented |
AM0806 # 05 Y:2020 | 05 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,610 | $1,000 | Not Implemented |
AM0806 # 06 Y:2020 | 06 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,580 | $2,250 | Not Implemented |
AM0806 # 07 Y:2020 | 07 | 2020 | USE SYNTHETIC LUBRICANT | $1,970 | $300 | Not Implemented |
AM0806 # 08 Y:2020 | 08 | 2020 | USE COMPRESSOR AIR FILTERS | $1,040 | $135 | Implemented |
AM0806 # 09 Y:2020 | 09 | 2020 | PAY UTILITY BILLS ON TIME | $484 | $0 | Implemented |
AM0807 # 01 Y:2020 | 01 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $12,243 | $320 | Not Implemented |
AM0807 # 02 Y:2020 | 02 | 2020 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $10,390 | $800 | Not Implemented |
AM0807 # 03 Y:2020 | 03 | 2020 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $9,795 | $2,700 | Not Implemented |
AM0807 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,453 | $1,000 | Implemented |
AM0807 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,462 | $1,138 | Implemented |
AM0807 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,095 | $6,130 | Implemented |
AM0807 # 07 Y:2020 | 07 | 2020 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $1,430 | $4,570 | Implemented |