ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MU0048 # 04 Y:2024 | 04 | 2024 | INSTALL OCCUPANCY SENSORS | $184 | $84 | n/a |
MU0048 # 05 Y:2024 | 05 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $285 | $367 | n/a |
MU0048 # 06 Y:2024 | 06 | 2024 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,133 | $555 | n/a |
MU0048 # 07 Y:2024 | 07 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $5,850 | $45,513 | n/a |
SD0659 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $150,247 | $333,540 | Not Implemented |
SD0659 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $48,096 | $0 | Not Implemented |
SD0659 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $86,343 | $34,702 | Implemented |
SD0659 # 04 Y:2024 | 04 | 2024 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $78,160 | $16,180 | Not Implemented |
SD0659 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,955 | $2,109 | Not Implemented |
SD0659 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,742 | $3,181 | Not Implemented |
SD0659 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $86,038 | $57,435 | Not Implemented |
SD0659 # 08 Y:2024 | 08 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $42,562 | $0 | Implemented |
SD0659 # 09 Y:2024 | 09 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,401 | $2,880 | Implemented |
SD0659 # 10 Y:2024 | 10 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,080 | $3,360 | Not Implemented |
SD0659 # 11 Y:2024 | 11 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $53,887 | $3,345 | Not Implemented |
SD0659 # 12 Y:2024 | 12 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $56,412 | $3,345 | Not Implemented |
SD0659 # 13 Y:2024 | 13 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $55,674 | $3,278 | Not Implemented |
SD0659 # 14 Y:2024 | 14 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $130,069 | $201,000 | Not Implemented |
UF0613 # 01 Y:2024 | 01 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $942,391 | $22,400 | n/a |
UF0613 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $500,050 | $518,990 | n/a |
UF0613 # 03 Y:2024 | 03 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $263,426 | $265,574 | n/a |
UF0613 # 04 Y:2024 | 04 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $106,816 | $25,400 | n/a |
UF0613 # 05 Y:2024 | 05 | 2024 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $92,260 | $61,871 | n/a |
UF0613 # 06 Y:2024 | 06 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $73,600 | $322,608 | n/a |
UF0613 # 07 Y:2024 | 07 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $47,434 | $0 | n/a |