Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsNAICS | 32611 | Plastics Packaging Materials and Unlaminated Film and Sheet Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0975 # 03 Y:2017 | 03 | 2017 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $17,029 | $68 | Implemented |
UD0975 # 12 Y:2017 | 12 | 2017 | INSTALL OCCUPANCY SENSORS | $3,441 | $1,931 | Implemented |
UD0975 # 11 Y:2017 | 11 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $45,148 | $47,000 | Implemented |
UD0975 # 10 Y:2017 | 10 | 2017 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $4,642 | $5,000 | Not Implemented |
UD0975 # 09 Y:2017 | 09 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $1,684 | $1,500 | Implemented |
UD0975 # 08 Y:2017 | 08 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,964 | $2,000 | Not Implemented |
UD0975 # 07 Y:2017 | 07 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,640 | $1,600 | Implemented |
UD0975 # 06 Y:2017 | 06 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $16,737 | $2,000 | Not Implemented |
UD0975 # 05 Y:2017 | 05 | 2017 | COVER OPEN TANKS | $29,884 | $2,350 | Not Implemented |
UD0975 # 04 Y:2017 | 04 | 2017 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $9,406 | $500 | Not Implemented |
UD0975 # 02 Y:2017 | 02 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,179 | $0 | Implemented |
UD0975 # 01 Y:2017 | 01 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $14,600 | $0 | Implemented |
UD0961 # 01 Y:2017 | 01 | 2017 | USE RADIANT HEATER FOR SPOT HEATING | $23,931 | $14,250 | Not Implemented |
UD0961 # 08 Y:2017 | 08 | 2017 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $18,094 | $103,500 | Not Implemented |
UD0961 # 07 Y:2017 | 07 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,802 | $3,700 | Not Implemented |
UD0961 # 06 Y:2017 | 06 | 2017 | REDUCE FLUID FLOW RATES | $5,273 | $1,000 | Not Implemented |
UD0961 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,937 | $1,000 | Not Implemented |
UD0961 # 04 Y:2017 | 04 | 2017 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,969 | $23,750 | Not Implemented |
UD0961 # 03 Y:2017 | 03 | 2017 | DEVELOP A REPAIR/REPLACE POLICY | $1,272 | $4,748 | Not Implemented |
UD0961 # 02 Y:2017 | 02 | 2017 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $4,308 | $0 | Not Implemented |