Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
522
matching recommendationsNAICS | 326113 | Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0170 # 10 Y:2023 | 10 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $195 | $600 | Not Implemented |
DL0212 # 10 Y:2022 | 10 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,304 | $22,424 | Not Implemented |
DL0212 # 09 Y:2022 | 09 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $278 | $210 | Not Implemented |
DL0212 # 08 Y:2022 | 08 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,587 | $13,450 | Not Implemented |
DL0212 # 07 Y:2022 | 07 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $11,396 | $21,500 | Not Implemented |
DL0212 # 06 Y:2022 | 06 | 2022 | USE OPTIMUM THICKNESS INSULATION | $692 | $2,233 | Not Implemented |
DL0212 # 05 Y:2022 | 05 | 2022 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $3,655 | $5,200 | Not Implemented |
DL0212 # 04 Y:2022 | 04 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,199 | $6,100 | Not Implemented |
DL0212 # 03 Y:2022 | 03 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $634 | $495 | Not Implemented |
DL0212 # 02 Y:2022 | 02 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,912 | $5,000 | Not Implemented |
DL0212 # 01 Y:2022 | 01 | 2022 | REPAIR FAULTY LOUVERS AND DAMPERS | $20,616 | $975 | Not Implemented |
MZ0335 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $558 | $480 | Implemented |
MZ0335 # 02 Y:2022 | 02 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,654 | $7,600 | Implemented |
MZ0335 # 03 Y:2022 | 03 | 2022 | INSULATE BARE EQUIPMENT | $1,834 | $680 | Implemented |
MZ0335 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $701 | $1,200 | Implemented |
MZ0335 # 05 Y:2022 | 05 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $106,813 | $957,388 | Not Implemented |
MZ0335 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $759 | $1,330 | Implemented |
MZ0335 # 07 Y:2022 | 07 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,141 | $9,100 | Not Implemented |
MZ0335 # 08 Y:2022 | 08 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $449 | $200 | Not Implemented |
MI0406 # 01 Y:2022 | 01 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $17,298 | $45,090 | Implemented |
MI0406 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,075 | $5,674 | Implemented |
MI0406 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,550 | $2,031 | Implemented |
MI0406 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,468 | $15,450 | Implemented |
MI0406 # 05 Y:2022 | 05 | 2022 | OPTIMIZE PLANT POWER FACTOR | $5,579 | $15,821 | Implemented |
MI0406 # 06 Y:2022 | 06 | 2022 | ELIMINATE/REDUCE AN OPERATION | $4,770 | $960 | Implemented |