Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
530
matching recommendationsNAICS | 326113 | Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0335 # 07 Y:2022 | 07 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,141 | $9,100 | Not Implemented |
MZ0335 # 08 Y:2022 | 08 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $449 | $200 | Not Implemented |
MI0406 # 01 Y:2022 | 01 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $17,298 | $45,090 | Implemented |
MI0406 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,075 | $5,674 | Implemented |
MI0406 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,550 | $2,031 | Implemented |
MI0406 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,468 | $15,450 | Implemented |
MI0406 # 05 Y:2022 | 05 | 2022 | OPTIMIZE PLANT POWER FACTOR | $5,579 | $15,821 | Implemented |
MI0406 # 06 Y:2022 | 06 | 2022 | ELIMINATE/REDUCE AN OPERATION | $4,770 | $960 | Implemented |
MI0406 # 07 Y:2022 | 07 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,016 | $100 | Not Implemented |
LE0488 # 01 Y:2020 | 01 | 2020 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $1,217 | $40 | Not Implemented |
LE0488 # 02 Y:2020 | 02 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,201 | $360 | Implemented |
LE0488 # 03 Y:2020 | 03 | 2020 | REPLACE DC EQUIPMENT WITH AC EQUIPMENT | $82,690 | $150,334 | Implemented |
LE0488 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,465 | $13,000 | Implemented |
LE0488 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,995 | $12,420 | Implemented |
LE0488 # 06 Y:2020 | 06 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $788 | $2,200 | Implemented |
LE0488 # 07 Y:2020 | 07 | 2020 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $2,905 | $9,300 | Implemented |
UD1009 # 01 Y:2020 | 01 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $32,116 | $0 | Implemented |
UD1009 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,826 | $1,000 | Implemented |
UD1009 # 03 Y:2020 | 03 | 2020 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $78,282 | $44,250 | Not Implemented |
UD1009 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,717 | $4,388 | Implemented |
UD1009 # 05 Y:2020 | 05 | 2020 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $107,302 | $83,000 | Implemented |
UD1009 # 06 Y:2020 | 06 | 2020 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $100,517 | $151,300 | Not Implemented |
UD1009 # 07 Y:2020 | 07 | 2020 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $73,844 | $147,736 | Not Implemented |
OK1017 # 01 Y:2019 | 01 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,604 | $17,500 | Not Implemented |
OK1017 # 02 Y:2019 | 02 | 2019 | INSTALL / REPAIR INSULATION ON STEAM LINES | $10,627 | $231 | Not Implemented |