Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
361
matching recommendationsNAICS | 32612 | Plastics Pipe, Pipe Fitting, and Unlaminated Profile Shape Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0559 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $704 | $450 | Implemented |
LE0559 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $768 | $100 | Implemented |
OK1085 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,322 | $2,730 | Implemented |
OK1085 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,853 | $0 | Implemented |
OK1085 # 04 Y:2023 | 04 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $15,984 | $2,567 | Implemented |
OK1085 # 05 Y:2023 | 05 | 2023 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $564 | $0 | Implemented |
DL0210 # 03 Y:2022 | 03 | 2022 | INSTALL SET-BACK TIMERS | $4,951 | $2,500 | Implemented |
DL0210 # 02 Y:2022 | 02 | 2022 | INSTALL SET-BACK TIMERS | $14,339 | $1,650 | Implemented |
LE0517 # 06 Y:2022 | 06 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $125 | $480 | Implemented |
LE0517 # 03 Y:2022 | 03 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $52,000 | $100,000 | Implemented |
LE0517 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $603 | $40 | Implemented |
OK1065 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $29,263 | $0 | Implemented |
OK1065 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,433 | $2,429 | Implemented |
OK1065 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,273 | $21,539 | Implemented |
OK1065 # 01 Y:2022 | 01 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,073 | $12,233 | Implemented |
AM0837 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,092 | $1,225 | Implemented |
AM0837 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $955 | $75 | Implemented |
AM0837 # 04 Y:2022 | 04 | 2022 | PAY UTILITY BILLS ON TIME | $197 | $0 | Implemented |
DL0198 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,850 | $0 | Implemented |
DL0198 # 02 Y:2021 | 02 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,800 | $0 | Implemented |
DL0198 # 05 Y:2021 | 05 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,240 | $2,500 | Implemented |
DL0198 # 09 Y:2021 | 09 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,740 | $14,428 | Implemented |
OK1057 # 02 Y:2021 | 02 | 2021 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $12,483 | $56,000 | Implemented |
OK1057 # 04 Y:2021 | 04 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,960 | $0 | Implemented |
OK1057 # 01 Y:2021 | 01 | 2021 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $10,601 | $1,701 | Implemented |