ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0659 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $86,343 | $34,702 | Implemented |
SD0659 # 09 Y:2024 | 09 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,401 | $2,880 | Implemented |
SD0659 # 08 Y:2024 | 08 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $42,562 | $0 | Implemented |
UF0611 # 03 Y:2024 | 03 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $30,134 | $5,900 | Implemented |
UF0611 # 04 Y:2024 | 04 | 2024 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $26,100 | $0 | Implemented |
UF0611 # 08 Y:2024 | 08 | 2024 | INSTALL TURBULATORS | $2,454 | $3,750 | Implemented |
UF0611 # 01 Y:2024 | 01 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $99,213 | $111,120 | Implemented |
UF0611 # 05 Y:2024 | 05 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $19,576 | $19,104 | Implemented |
UF0592 # 05 Y:2023 | 05 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $9,922 | $11,796 | Implemented |
UF0592 # 08 Y:2023 | 08 | 2023 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $1,672 | $1,200 | Implemented |
UF0592 # 03 Y:2023 | 03 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $30,274 | $30,607 | Implemented |
UF0592 # 09 Y:2023 | 09 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,580 | $600 | Implemented |
UF0592 # 02 Y:2023 | 02 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $56,023 | $88,370 | Implemented |
UF0592 # 07 Y:2023 | 07 | 2023 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $2,981 | $508 | Implemented |
AM0877 # 03 Y:2023 | 03 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $18,290 | $74,067 | Implemented |
UF0592 # 04 Y:2023 | 04 | 2023 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $15,287 | $18,600 | Implemented |
AM0877 # 07 Y:2023 | 07 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,060 | $0 | Implemented |
AM0877 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,700 | $32,850 | Implemented |
UF0592 # 10 Y:2023 | 10 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $62,417 | $10,000 | Implemented |
AM0877 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $35,600 | $148,000 | Implemented |
AM0877 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $16,440 | $105 | Implemented |
AM0877 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,900 | $60,360 | Implemented |
DL0215 # 04 Y:2023 | 04 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $17,640 | $3,000 | Implemented |
DL0215 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $222,700 | $184,000 | Implemented |
DL0194 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,325 | $475 | Implemented |