Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,921
matching recommendationsNAICS | 32619 | Other Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0192 # 01 Y:2015 | 01 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,801 | $1,160 | Implemented |
MZ0192 # 02 Y:2015 | 02 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $11,360 | $6,100 | Implemented |
MZ0192 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,247 | $920 | Implemented |
MZ0192 # 04 Y:2015 | 04 | 2015 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $8,654 | $19,200 | Not Implemented |
MZ0192 # 05 Y:2015 | 05 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,211 | $0 | Implemented |
OK0929 # 01 Y:2015 | 01 | 2015 | OPTIMIZE PLANT POWER FACTOR | $26,164 | $68,769 | Not Implemented |
OK0929 # 02 Y:2015 | 02 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $9,329 | $20,400 | Not Implemented |
OK0929 # 03 Y:2015 | 03 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $82,236 | $72,000 | Not Implemented |
NC0554 # 01 Y:2015 | 01 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,085 | $12,500 | Implemented |
NC0554 # 02 Y:2015 | 02 | 2015 | INSULATE BARE EQUIPMENT | $10,751 | $8,568 | Not Implemented |
NC0554 # 03 Y:2015 | 03 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,597 | $4,400 | Implemented |
NC0554 # 04 Y:2015 | 04 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,465 | $12,000 | Implemented |
NC0554 # 05 Y:2015 | 05 | 2015 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $3,916 | $4,500 | Not Implemented |
NC0554 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,384 | $100 | Implemented |
NC0554 # 07 Y:2015 | 07 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,043 | $9,000 | Not Implemented |
NC0554 # 08 Y:2015 | 08 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $147 | $150 | Implemented |
NC0554 # 09 Y:2015 | 09 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $587 | $100 | Not Implemented |
NC0554 # 10 Y:2015 | 10 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $2,829 | $4,258 | Implemented |
NC0553 # 01 Y:2015 | 01 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $63,028 | $500 | Implemented |
NC0553 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,894 | $68,084 | Implemented |
NC0553 # 03 Y:2015 | 03 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,721 | $1,206 | Implemented |
NC0553 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $542 | $160 | Implemented |
NC0553 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $432 | $694 | Implemented |
NC0553 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $363 | $1,170 | Implemented |
NC0553 # 07 Y:2015 | 07 | 2015 | INSULATE BARE EQUIPMENT | $5,143 | $9,886 | Implemented |