matching recommendationsNAICS | 326199 | All Other Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0347 # 06 Y:2008 | 06 | 2008 | INSTALL AUTOMATIC STACK DAMPER | $29,890 | $8,100 | Not Implemented |
UM0347 # 04 Y:2008 | 04 | 2008 | INSTALL OCCUPANCY SENSORS | $1,503 | $500 | Not Implemented |
UM0347 # 03 Y:2008 | 03 | 2008 | COVER OPEN TANKS | $2,233 | $1,046 | Not Implemented |
UM0347 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,545 | $6,240 | Not Implemented |
UM0347 # 05 Y:2008 | 05 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $452 | $422 | Not Implemented |
UM0347 # 01 Y:2008 | 01 | 2008 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,638 | $8,898 | Not Implemented |
DL0025 # 06 Y:2008 | 06 | 2008 | UPGRADE CONTROLS ON COMPRESSORS | $3,964 | $0 | Not Implemented |
DL0025 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,919 | $30,000 | Implemented |
DL0025 # 04 Y:2008 | 04 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,600 | $0 | Not Implemented |
DL0025 # 03 Y:2008 | 03 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $36,900 | $0 | Implemented |
DL0025 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,976 | $0 | Implemented |
DL0025 # 01 Y:2008 | 01 | 2008 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $1,078 | $0 | Not Implemented |
SD0410 # 10 Y:2008 | 10 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,041 | $5,849 | Not Implemented |
SD0410 # 11 Y:2008 | 11 | 2008 | INSTALL SKYLIGHTS | $7,467 | $22,980 | Implemented |
SD0410 # 07 Y:2008 | 07 | 2008 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $22,978 | $11,522 | Not Implemented |
SD0410 # 12 Y:2008 | 12 | 2008 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,185 | $0 | Not Implemented |
SD0410 # 08 Y:2008 | 08 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,624 | $24,471 | Not Implemented |
SD0410 # 09 Y:2008 | 09 | 2008 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $10,867 | $500 | Not Implemented |
SD0410 # 01 Y:2008 | 01 | 2008 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $824,374 | $6,360,000 | Not Implemented |
SD0410 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $33,992 | $2,250 | Implemented |
SD0410 # 02 Y:2008 | 02 | 2008 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $41,267 | $0 | Not Implemented |
SD0410 # 05 Y:2008 | 05 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $26,826 | $81,570 | Not Implemented |
SD0410 # 04 Y:2008 | 04 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $28,203 | $56,758 | Implemented |
SD0410 # 06 Y:2008 | 06 | 2008 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $24,980 | $0 | Implemented |
IC0144 # 05 Y:2008 | 05 | 2008 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $68 | $0 | Implemented |