Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
89
matching recommendationsNAICS | 326199 | All Other Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0396 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,908 | $2,020 | Implemented |
MI0396 # 06 Y:2021 | 06 | 2021 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,320 | $1,290 | Not Implemented |
MI0396 # 03 Y:2021 | 03 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,464 | $3,060 | Not Implemented |
MI0396 # 02 Y:2021 | 02 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $27,588 | $100 | Not Implemented |
MI0396 # 05 Y:2021 | 05 | 2021 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,263 | $1,487 | Not Implemented |
MI0396 # 01 Y:2021 | 01 | 2021 | PAY UTILITY BILLS ON TIME | $27,408 | $0 | Implemented |
TT0262 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,405 | $1,640 | Not Implemented |
TT0262 # 04 Y:2021 | 04 | 2021 | INSULATE BARE EQUIPMENT | $4,646 | $3,879 | Implemented |
TT0262 # 01 Y:2021 | 01 | 2021 | USE SOLAR HEAT FOR HEAT | $44,686 | $476,000 | Not Implemented |
TT0262 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,023 | $2,762 | Implemented |
TT0262 # 02 Y:2021 | 02 | 2021 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $7,441 | $15,000 | Not Implemented |
UU0190 # 03 Y:2021 | 03 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,184 | $2,500 | Not Implemented |
UU0190 # 02 Y:2021 | 02 | 2021 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $8,939 | $3,000 | Not Implemented |
UU0190 # 04 Y:2021 | 04 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $2,942 | $2,900 | Not Implemented |
UU0190 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,058 | $778 | Not Implemented |
UU0190 # 01 Y:2021 | 01 | 2021 | INSULATE BARE EQUIPMENT | $9,772 | $5,582 | Not Implemented |
CL2112 # 02 Y:2021 | 02 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,367 | $0 | n/a |
CL2112 # 05 Y:2021 | 05 | 2021 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $192 | $0 | n/a |
CL2112 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,967 | $17,500 | n/a |
CL2112 # 03 Y:2021 | 03 | 2021 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $293 | $260 | n/a |
CL2112 # 01 Y:2021 | 01 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $2,080 | $5,100 | n/a |
MI0390 # 02 Y:2021 | 02 | 2021 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $4,349 | $7,564 | Not Implemented |
MI0390 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,676 | $3,477 | Implemented |
MI0390 # 01 Y:2021 | 01 | 2021 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $8,273 | $1,040 | Implemented |
MI0390 # 04 Y:2021 | 04 | 2021 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $1,586 | $1,120 | Not Implemented |