Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
39
matching recommendationsNAICS | 326291 | Rubber Product Manufacturing for Mechanical Use |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2211 # 07 Y:2022 | 07 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,765 | $0 | Implemented |
UL2211 # 06 Y:2022 | 06 | 2022 | USE SOLAR HEAT TO HEAT WATER | $60,938 | $150,000 | Not Implemented |
UL2211 # 05 Y:2022 | 05 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $96,458 | $783,531 | Not Implemented |
UL2211 # 04 Y:2022 | 04 | 2022 | OPTIMIZE PLANT POWER FACTOR | $61,887 | $45,461 | Implemented |
UL2211 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,815 | $0 | Implemented |
UL2211 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,806 | $20,000 | Not Implemented |
UL2211 # 01 Y:2022 | 01 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,600 | $15,000 | Not Implemented |
UK1703 # 02 Y:2017 | 02 | 2017 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $26,732 | $110,000 | Not Implemented |
UK1703 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,523 | $55,849 | Not Implemented |
UK1703 # 03 Y:2017 | 03 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $99 | $0 | Not Implemented |
UK1703 # 04 Y:2017 | 04 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $117 | $0 | Not Implemented |
UK1703 # 05 Y:2017 | 05 | 2017 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $16,465 | $1,000 | Not Implemented |
UK1703 # 06 Y:2017 | 06 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,466 | $0 | Not Implemented |
UK1703 # 07 Y:2017 | 07 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,135 | $0 | Not Implemented |
UK1703 # 08 Y:2017 | 08 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,384 | $13,000 | Not Implemented |
UK1703 # 09 Y:2017 | 09 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,471 | $1,968 | Not Implemented |
UK1703 # 10 Y:2017 | 10 | 2017 | DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING | $131 | $0 | Not Implemented |
UK1703 # 11 Y:2017 | 11 | 2017 | USE MINIMUM STEAM OPERATING PRESSURE | $920 | $0 | Not Implemented |
UK1703 # 12 Y:2017 | 12 | 2017 | INSULATE BARE EQUIPMENT | $720 | $296 | Not Implemented |
UK1703 # 13 Y:2017 | 13 | 2017 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $451 | $1,150 | Not Implemented |
UK1610 # 09 Y:2016 | 09 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $63 | $0 | Not Implemented |
UK1610 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,688 | $4,985 | Implemented |
UK1610 # 02 Y:2016 | 02 | 2016 | INSTALL OCCUPANCY SENSORS | $374 | $148 | Implemented |
UK1610 # 03 Y:2016 | 03 | 2016 | DISCONNECT BALLASTS | $92 | $34 | Not Implemented |
UK1610 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $240 | $470 | Not Implemented |