Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
175
matching recommendationsNAICS | 326299 | All Other Rubber Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0455 # 04 Y:2012 | 04 | 2012 | INSULATE BARE EQUIPMENT | $6,023 | $2,440 | Implemented |
WV0455 # 05 Y:2012 | 05 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $3,160 | $5,680 | Not Implemented |
WV0455 # 06 Y:2012 | 06 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,600 | $3,294 | Implemented |
WV0455 # 07 Y:2012 | 07 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,374 | $4,330 | Not Implemented |
WV0455 # 08 Y:2012 | 08 | 2012 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $1,918 | $4,850 | Not Implemented |
WV0455 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,863 | $1,706 | Implemented |
WV0455 # 10 Y:2012 | 10 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,663 | $2,117 | Implemented |
WV0455 # 11 Y:2012 | 11 | 2012 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,644 | $1,000 | Implemented |
WV0455 # 12 Y:2012 | 12 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,418 | $1,000 | Implemented |
WV0455 # 13 Y:2012 | 13 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $1,157 | $841 | Implemented |
WV0455 # 14 Y:2012 | 14 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,149 | $4,320 | Not Implemented |
WV0455 # 15 Y:2012 | 15 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $845 | $70 | Implemented |
WV0455 # 16 Y:2012 | 16 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $712 | $620 | Implemented |
WV0455 # 17 Y:2012 | 17 | 2012 | USE PHOTOCELL CONTROLS | $645 | $620 | Implemented |
WV0455 # 18 Y:2012 | 18 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $377 | $500 | Implemented |
UD0859 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,512 | $10,150 | Not Implemented |
UD0859 # 02 Y:2012 | 02 | 2012 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $581 | $600 | Implemented |
UD0859 # 03 Y:2012 | 03 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,313 | $100 | Not Implemented |
UD0859 # 04 Y:2012 | 04 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,041 | $2,000 | Not Implemented |
UD0859 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,953 | $1,000 | Implemented |
UD0859 # 06 Y:2012 | 06 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $20,256 | $6,033 | Implemented |
UD0859 # 07 Y:2012 | 07 | 2012 | REDUCE EXCESS STEAM BLEEDING | $20,148 | $0 | Implemented |
UD0859 # 08 Y:2012 | 08 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,768 | $2,000 | Implemented |
UD0859 # 09 Y:2012 | 09 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,869 | $10,000 | Not Implemented |
UD0859 # 10 Y:2012 | 10 | 2012 | REDUCE EXCESSIVE BOILER BLOWDOWN | $4,657 | $5,000 | Not Implemented |