Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,688
matching recommendationsNAICS | 327 | Nonmetallic Mineral Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0554 # 06 Y:2018 | 06 | 2018 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $6,147 | $21,264 | Implemented |
WV0554 # 07 Y:2018 | 07 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,081 | $5,593 | Implemented |
WV0554 # 08 Y:2018 | 08 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $1,406 | $632 | Implemented |
WV0554 # 09 Y:2018 | 09 | 2018 | MINIMIZE WATER USAGE | $1,354 | $700 | Implemented |
WV0554 # 10 Y:2018 | 10 | 2018 | INSTALL SET-BACK TIMERS | $974 | $2,132 | Not Implemented |
WV0554 # 11 Y:2018 | 11 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $424 | $133 | Implemented |
WV0554 # 12 Y:2018 | 12 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $221 | $516 | Implemented |
OK0981 # 01 Y:2018 | 01 | 2018 | UPGRADE CONTROLS ON COMPRESSORS | $124,716 | $75,000 | Implemented |
OK0981 # 02 Y:2018 | 02 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,815 | $0 | Not Implemented |
OK0981 # 03 Y:2018 | 03 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $16,309 | $4,937 | Not Implemented |
OK0981 # 04 Y:2018 | 04 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,343 | $69,050 | Not Implemented |
OK0981 # 05 Y:2018 | 05 | 2018 | INSTALL WASTE HEAT BOILER TO PROVIDE DIRECT POWER | $353,111 | $2,500,000 | Not Implemented |
OK0981 # 06 Y:2018 | 06 | 2018 | OPTIMIZE PLANT POWER FACTOR | $11,423 | $50,570 | Not Implemented |
TR0007 # 01 Y:2018 | 01 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $34,558 | $3,000 | Implemented |
TR0007 # 02 Y:2018 | 02 | 2018 | OPTIMIZE PLANT POWER FACTOR | $5,927 | $22,500 | Implemented |
TR0007 # 03 Y:2018 | 03 | 2018 | RECYCLE FLUORESCENT LAMPS | $10,606 | $23,530 | Implemented |
TR0007 # 04 Y:2018 | 04 | 2018 | METER WASTE WATER | $6,760 | $2,650 | Not Implemented |
TR0007 # 05 Y:2018 | 05 | 2018 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $5,572 | $500 | Implemented |
TR0007 # 06 Y:2018 | 06 | 2018 | INSTALL OCCUPANCY SENSORS | $4,304 | $6,855 | Implemented |
TR0007 # 07 Y:2018 | 07 | 2018 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $750 | $2,212 | Not Implemented |
TR0007 # 08 Y:2018 | 08 | 2018 | INSULATE BARE EQUIPMENT | $421 | $38 | Implemented |
TR0007 # 09 Y:2018 | 09 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $109 | $195 | Implemented |
AS0444 # 01 Y:2017 | 01 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $33,358 | $4,325 | Not Implemented |
AS0444 # 02 Y:2017 | 02 | 2017 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,643 | $872 | Implemented |
AS0444 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,007 | $100 | Implemented |