IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

90

matching recommendations
Reset
NAICS 327 Nonmetallic Mineral Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UA0014 # 02 Y:2008 02 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,143 $1,040 Implemented
UA0014 # 03 Y:2008 03 2008 RECOVER WASTE HEAT FROM EQUIPMENT $2,493 $2,877 Not Implemented
UA0014 # 04 Y:2008 04 2008 OPTIMIZE PLANT POWER FACTOR $5,800 $14,850 Not Implemented
UA0014 # 06 Y:2008 06 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,934 $13,520 Not Implemented
UA0014 # 07 Y:2008 07 2008 SHUT OFF PILOTS IN STANDBY EQUIPMENT $457 $72 Implemented
UA0014 # 08 Y:2008 08 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,943 $1,164 Not Implemented
UA0014 # 09 Y:2008 09 2008 INSTALL OCCUPANCY SENSORS $2,288 $770 Not Implemented
UA0014 # 10 Y:2008 10 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $644 $700 Not Implemented
UA0014 # 11 Y:2008 11 2008 INSTALL TIMERS AND/OR THERMOSTATS $1,430 $952 Implemented
MS0275 # 06 Y:2005 06 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,823 $2,271 Not Implemented
MS0275 # 05 Y:2005 05 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,020 $9,612 Implemented
MS0275 # 04 Y:2005 04 2005 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,972 $15,438 Not Implemented
MS0275 # 03 Y:2005 03 2005 USE SYNTHETIC LUBRICANT $7,356 $3,025 Implemented
MS0275 # 02 Y:2005 02 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,066 $392 Implemented
MS0275 # 01 Y:2005 01 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,870 $34,746 Implemented