Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
269
matching recommendationsNAICS | 331 | Primary Metal Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0644 # 05 Y:2013 | 05 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $29,120 | $50 | Implemented |
AM0644 # 07 Y:2013 | 07 | 2013 | INSTALL SKYLIGHTS | $11,090 | $7,840 | Not Implemented |
AM0644 # 04 Y:2013 | 04 | 2013 | OPTIMIZE PLANT POWER FACTOR | $43,700 | $147,000 | Implemented |
AM0644 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $45,950 | $50,800 | Implemented |
AM0644 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $51,450 | $2,000 | Implemented |
AM0644 # 01 Y:2013 | 01 | 2013 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $211,550 | $5,000 | Implemented |
UA3030 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $71,086 | $800 | Implemented |
UA3030 # 02 Y:2013 | 02 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $76,352 | $32,825 | Not Implemented |
UA3030 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $115,835 | $27,390 | Not Implemented |
UD0888 # 10 Y:2013 | 10 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $695 | $0 | Not Implemented |
UK1313 # 08 Y:2013 | 08 | 2013 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,313 | $0 | Implemented |
UK1313 # 17 Y:2013 | 17 | 2013 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,679 | $5,000 | Not Implemented |
UK1313 # 07 Y:2013 | 07 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,011 | $0 | Implemented |
UK1313 # 16 Y:2013 | 16 | 2013 | INSULATE BARE EQUIPMENT | $6,807 | $894 | Not Implemented |
UK1313 # 09 Y:2013 | 09 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,246 | $3,000 | Not Implemented |
UK1313 # 14 Y:2013 | 14 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $3,770 | $9,750 | Implemented |
UK1313 # 10 Y:2013 | 10 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $695 | $0 | Not Implemented |
UD0888 # 12 Y:2013 | 12 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $20,092 | $0 | Implemented |
UD0888 # 14 Y:2013 | 14 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $3,770 | $0 | Implemented |
UD0888 # 11 Y:2013 | 11 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,284 | $15,000 | Implemented |
UD0888 # 13 Y:2013 | 13 | 2013 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,444 | $4,500 | Not Implemented |
UD0888 # 01 Y:2013 | 01 | 2013 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $396 | $5,000 | Implemented |
UD0888 # 02 Y:2013 | 02 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $841 | $0 | Implemented |
UD0888 # 03 Y:2013 | 03 | 2013 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $23,080 | $10,000 | Not Implemented |
UD0888 # 04 Y:2013 | 04 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,510 | $5,000 | Implemented |