Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
46
matching recommendationsNAICS | 3315 | Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0298 # 06 Y:2010 | 06 | 2010 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $125 | $274 | Not Implemented |
SU0298 # 02 Y:2010 | 02 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,096 | $0 | Not Implemented |
SU0298 # 01 Y:2010 | 01 | 2010 | PAY BILLS ON TIME TO AVOID LATE FEES | $21,457 | $0 | Not Implemented |
SU0298 # 07 Y:2010 | 07 | 2010 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $35,873 | $81,798 | Not Implemented |
SU0298 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $792 | $266 | Not Implemented |
SU0298 # 08 Y:2010 | 08 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,123 | $45,613 | Not Implemented |
SU0298 # 04 Y:2010 | 04 | 2010 | INSTALL OCCUPANCY SENSORS | $431 | $86 | Not Implemented |
SU0298 # 03 Y:2010 | 03 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,218 | $1,248 | Not Implemented |
SU0298 # 09 Y:2010 | 09 | 2010 | OPTIMIZE PLANT POWER FACTOR | $4,349 | $17,933 | Not Implemented |
SU0280 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,497 | $378 | Implemented |
SU0280 # 11 Y:2009 | 11 | 2009 | OPTIMIZE PLANT POWER FACTOR | $2,725 | $7,949 | Implemented |
SU0280 # 10 Y:2009 | 10 | 2009 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $644 | $1,009 | Not Implemented |
SU0280 # 09 Y:2009 | 09 | 2009 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $47,225 | $73,508 | Not Implemented |
SU0280 # 08 Y:2009 | 08 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $344 | $405 | Not Implemented |
SU0280 # 07 Y:2009 | 07 | 2009 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,497 | $3,768 | Implemented |
SU0280 # 06 Y:2009 | 06 | 2009 | INSTALL OCCUPANCY SENSORS | $4,873 | $1,477 | Implemented |
SU0280 # 04 Y:2009 | 04 | 2009 | USE SYNTHETIC LUBRICANT | $1,438 | $0 | Not Implemented |
SU0280 # 03 Y:2009 | 03 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,445 | $0 | Implemented |
SU0280 # 02 Y:2009 | 02 | 2009 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,999 | $0 | Implemented |
SU0280 # 01 Y:2009 | 01 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,297 | $0 | Implemented |
SU0237 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,224 | $7,782 | Implemented |
SU0237 # 03 Y:2006 | 03 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,173 | $0 | Implemented |
SU0237 # 06 Y:2006 | 06 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,115 | $219 | Implemented |
SU0237 # 05 Y:2006 | 05 | 2006 | DISCONNECT BALLASTS | $82 | $0 | Not Implemented |
SU0237 # 04 Y:2006 | 04 | 2006 | USE SYNTHETIC LUBRICANT | $606 | $0 | Implemented |