IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

51

matching recommendations
Reset
NAICS 3315 Foundries
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0521 # 07 Y:2014 07 2014 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,616 $2,313 Implemented
IA0521 # 08 Y:2014 08 2014 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,689 $350 Not Implemented
IA0521 # 06 Y:2014 06 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,158 $70 Implemented
IA0521 # 01 Y:2014 01 2014 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $116,438 $25,000 Implemented
IA0521 # 02 Y:2014 02 2014 INSULATE BARE EQUIPMENT $7,861 $500 Implemented
IA0521 # 03 Y:2014 03 2014 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $4,593 $1,750 Implemented
IA0521 # 04 Y:2014 04 2014 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $41,190 $3,600 Not Implemented
IA0521 # 05 Y:2014 05 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,258 $355 Not Implemented
IA0432 # 01 Y:2008 01 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $687 $330 Implemented
IA0432 # 12 Y:2008 12 2008 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $2,480 $5,333 Implemented
IA0432 # 09 Y:2008 09 2008 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $571 $1,650 Implemented
IA0432 # 11 Y:2008 11 2008 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $2,042 $930 Not Implemented
IA0432 # 06 Y:2008 06 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $416 $322 Implemented
IA0432 # 08 Y:2008 08 2008 RECOVER WASTE HEAT FROM EQUIPMENT $16,295 $3,442 Not Implemented
IA0432 # 03 Y:2008 03 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,859 $620 Implemented
IA0432 # 05 Y:2008 05 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $979 $17 Implemented
IA0432 # 10 Y:2008 10 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,529 $1,781 Not Implemented
IA0432 # 07 Y:2008 07 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $423 $143 Implemented
IA0432 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $986 $67 Not Implemented
IA0432 # 02 Y:2008 02 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,099 $1,884 Implemented
IA0412 # 09 Y:2007 09 2007 REDUCE SCRAP PRODUCTION $33,433 $4,000 Not Implemented
IA0412 # 08 Y:2007 08 2007 IMPROVE COMBUSTION CONTROL CAPABILITY $6,996 $500 Not Implemented
IA0412 # 01 Y:2007 01 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,810 $1,864 Implemented
IA0412 # 02 Y:2007 02 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,305 $2,775 Implemented
IA0412 # 03 Y:2007 03 2007 INSTALL OCCUPANCY SENSORS $671 $1,925 Not Implemented