Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
10,921
matching recommendationsNAICS | 332 | Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2412 # 02 Y:2024 | 02 | 2024 | PAY UTILITY BILLS ON TIME | $247 | $0 | n/a |
UC2412 # 03 Y:2024 | 03 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,358 | $0 | n/a |
UC2412 # 04 Y:2024 | 04 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,533 | $75 | n/a |
UC2412 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,630 | $1,300 | n/a |
UC2412 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $511 | $225 | n/a |
UC2412 # 07 Y:2024 | 07 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,217 | $900 | n/a |
UC2412 # 08 Y:2024 | 08 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $16,427 | $124,645 | n/a |
SJ0023 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,134 | $146,494 | n/a |
SJ0023 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $848 | $2,144 | n/a |
SJ0023 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $1,478 | $305 | n/a |
SJ0023 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,823 | $2,466 | n/a |
SJ0023 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,164 | $1,874 | n/a |
SJ0023 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,625 | $0 | n/a |
SJ0023 # 07 Y:2024 | 07 | 2024 | INSULATE BARE EQUIPMENT | $190 | $380 | n/a |
WV0666 # 01 Y:2024 | 01 | 2024 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $11,346 | $19,500 | Not Implemented |
WV0666 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,679 | $5,920 | Not Implemented |
WV0666 # 03 Y:2024 | 03 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $859 | $3,565 | Implemented |
WV0666 # 04 Y:2024 | 04 | 2024 | DEVELOP A REPAIR/REPLACE POLICY | $445 | $1,367 | Implemented |
WV0666 # 05 Y:2024 | 05 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $260 | $640 | Implemented |
WV0666 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $84 | $100 | Implemented |
AM0927 # 01 Y:2024 | 01 | 2024 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $86,006 | $120,000 | n/a |
AM0927 # 02 Y:2024 | 02 | 2024 | REDESIGN PROCESS | $7,085 | $34,585 | n/a |
AM0927 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $5,300 | $8,620 | n/a |
AM0927 # 04 Y:2024 | 04 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $841 | $166 | n/a |
AM0927 # 05 Y:2024 | 05 | 2024 | USE SYNTHETIC LUBRICANT | $295 | $166 | n/a |