Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
319
matching recommendationsNAICS | 332 | Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0251 # 05 Y:2021 | 05 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,641 | $128 | Not Implemented |
UA0251 # 02 Y:2021 | 02 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,595 | $100 | Not Implemented |
UA0251 # 03 Y:2021 | 03 | 2021 | OPTIMIZE PLANT POWER FACTOR | $24,626 | $4,208 | Not Implemented |
UA0251 # 04 Y:2021 | 04 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $7,062 | $1,190 | Not Implemented |
UA0251 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,263 | $2,002 | Not Implemented |
DL0200 # 07 Y:2021 | 07 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $16,430 | $36,000 | Not Implemented |
DL0200 # 06 Y:2021 | 06 | 2021 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $30,035 | $121,361 | Implemented |
DL0200 # 03 Y:2021 | 03 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,899 | $200 | Not Implemented |
DL0200 # 04 Y:2021 | 04 | 2021 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,182 | $0 | Implemented |
DL0200 # 05 Y:2021 | 05 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $9,055 | $3,275 | Not Implemented |
DL0200 # 08 Y:2021 | 08 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $75,171 | $186,000 | Not Implemented |
DL0200 # 02 Y:2021 | 02 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,955 | $0 | Implemented |
DL0200 # 09 Y:2021 | 09 | 2021 | USE HEAT PUMP FOR SPACE CONDITIONING | $3,788 | $5,060 | Not Implemented |
DL0200 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $16,029 | $0 | Not Implemented |
WV0617 # 10 Y:2021 | 10 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $450 | $638 | Implemented |
WV0617 # 01 Y:2021 | 01 | 2021 | INSTALL OCCUPANCY SENSORS | $10,582 | $19,059 | Not Implemented |
WV0617 # 02 Y:2021 | 02 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,162 | $5,562 | Not Implemented |
WV0617 # 05 Y:2021 | 05 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $973 | $655 | Implemented |
WV0617 # 06 Y:2021 | 06 | 2021 | OPTIMIZE PLANT POWER FACTOR | $811 | $2,732 | Implemented |
WV0617 # 08 Y:2021 | 08 | 2021 | DEVELOP A REPAIR/REPLACE POLICY | $648 | $2,086 | Implemented |
WV0617 # 07 Y:2021 | 07 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $743 | $2,460 | Not Implemented |
WV0617 # 09 Y:2021 | 09 | 2021 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $454 | $1,000 | Implemented |
WV0617 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,562 | $209 | Implemented |
WV0617 # 03 Y:2021 | 03 | 2021 | UPGRADE CONTROLS ON COMPRESSORS | $2,975 | $13,590 | Not Implemented |
SD0622 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,372 | $8,800 | Not Implemented |