Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
76
matching recommendationsNAICS | 33211 | Forging and Stamping |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0751 # 08 Y:2018 | 08 | 2018 | INSTALL OCCUPANCY SENSORS | $650 | $470 | Implemented |
AM0751 # 07 Y:2018 | 07 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,310 | $7 | Implemented |
AM0751 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,355 | $1,000 | Implemented |
AM0751 # 06 Y:2018 | 06 | 2018 | OPTIMIZE PLANT POWER FACTOR | $2,005 | $3,520 | Implemented |
AM0751 # 05 Y:2018 | 05 | 2018 | INSULATE BARE EQUIPMENT | $4,980 | $500 | Implemented |
AM0751 # 03 Y:2018 | 03 | 2018 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $27,160 | $10,000 | Not Implemented |
AM0751 # 02 Y:2018 | 02 | 2018 | OPTIMIZE PLANT POWER FACTOR | $12,430 | $20,750 | Implemented |
AM0751 # 01 Y:2018 | 01 | 2018 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $15,720 | $6,000 | Not Implemented |
AM0636 # 01 Y:2013 | 01 | 2013 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $12,500 | $5,000 | Implemented |
AM0636 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,600 | $900 | Implemented |
AM0636 # 03 Y:2013 | 03 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,250 | $2,280 | Not Implemented |
AM0636 # 04 Y:2013 | 04 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,758 | $14,762 | Not Implemented |
AM0636 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,670 | $2,595 | Not Implemented |
AM0636 # 06 Y:2013 | 06 | 2013 | USE SYNTHETIC LUBRICANT | $674 | $0 | Not Implemented |
AM0636 # 07 Y:2013 | 07 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,005 | $13 | Implemented |
AM0636 # 08 Y:2013 | 08 | 2013 | INSTALL OCCUPANCY SENSORS | $985 | $450 | Not Implemented |
TA0114 # 06 Y:2006 | 06 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $117 | $270 | Implemented |
TA0114 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $684 | $0 | Not Implemented |
TA0114 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,234 | $60 | Implemented |
TA0114 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $24,225 | $1,020 | Implemented |
TA0114 # 02 Y:2006 | 02 | 2006 | USE RADIANT HEATER FOR SPOT HEATING | $21,785 | $14,190 | Implemented |
TA0114 # 01 Y:2006 | 01 | 2006 | UPGRADE CONTROLS ON COMPRESSORS | $66,794 | $14,400 | Implemented |
AM0504 # 03 Y:2006 | 03 | 2006 | USE SYNTHETIC LUBRICANT | $1,155 | $0 | Not Implemented |
AM0504 # 02 Y:2006 | 02 | 2006 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $2,400 | $7,650 | Not Implemented |
AM0504 # 01 Y:2006 | 01 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,000 | $1,000 | Not Implemented |