IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

19

matching recommendations
Reset
NAICS 33211 Forging and Stamping
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0444 # 07 Y:2017 07 2017 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $119 $563 Implemented
SU0444 # 06 Y:2017 06 2017 UPGRADE OBSOLETE EQUIPMENT $162 $556 Implemented
SU0444 # 01 Y:2017 01 2017 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,081 $0 Implemented
SU0444 # 02 Y:2017 02 2017 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $527 $439 Not Implemented
SU0444 # 03 Y:2017 03 2017 ELIMINATE/REDUCE AN OPERATION $1,675 $1,780 Implemented
SU0444 # 04 Y:2017 04 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $145 $165 Not Implemented
SU0444 # 05 Y:2017 05 2017 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $25,853 $72,576 Not Implemented
SU0341 # 05 Y:2013 05 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $626 $137 Implemented
SU0341 # 04 Y:2013 04 2013 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $31 $0 Not Implemented
SU0341 # 03 Y:2013 03 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $299 $0 Implemented
SU0341 # 02 Y:2013 02 2013 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $314 $0 Implemented
SU0341 # 01 Y:2013 01 2013 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $357 $0 Implemented
SU0165 # 07 Y:2003 07 2003 UPGRADE CONTROLS ON COMPRESSORS $93,620 $94,691 Implemented
SU0165 # 06 Y:2003 06 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $8,763 $5,538 Not Implemented
SU0165 # 05 Y:2003 05 2003 OPTIMIZE PLANT POWER FACTOR $9,177 $20,736 Not Implemented
SU0165 # 04 Y:2003 04 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,503 $937 Implemented
SU0165 # 03 Y:2003 03 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,370 $17,064 Implemented
SU0165 # 02 Y:2003 02 2003 RECOVER AND REUSE SPENT ACID BATHS $30,138 $3,234 Implemented
SU0165 # 01 Y:2003 01 2003 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $99,450 $110,400 Implemented