Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
274
matching recommendationsNAICS | 332216 | Saw Blade and Handtool Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0161 # 03 Y:2016 | 03 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $328 | $719 | Implemented |
UA0161 # 02 Y:2016 | 02 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $632 | $100 | Implemented |
UA0161 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,411 | $8,838 | Implemented |
BD0482 # 03 Y:2016 | 03 | 2016 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,149 | $2,000 | Implemented |
BD0482 # 04 Y:2016 | 04 | 2016 | INSTALL OCCUPANCY SENSORS | $738 | $825 | Not Implemented |
BD0482 # 05 Y:2016 | 05 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $507 | $600 | Not Implemented |
BD0482 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $152 | $184 | Not Implemented |
BD0482 # 07 Y:2016 | 07 | 2016 | CONVERT TO ELECTROSTATIC POWDER COATING | $186,807 | $160,000 | Implemented |
BD0482 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,155 | $9,455 | Not Implemented |
BD0482 # 02 Y:2016 | 02 | 2016 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,096 | $840 | Implemented |
MZ0205 # 02 Y:2015 | 02 | 2015 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $1,559 | $0 | Implemented |
MZ0205 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,581 | $850 | Implemented |
MZ0205 # 04 Y:2015 | 04 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $397 | $0 | Implemented |
MZ0205 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $969 | $400 | Implemented |
MZ0205 # 01 Y:2015 | 01 | 2015 | INSULATE BARE EQUIPMENT | $771 | $1,050 | Not Implemented |
TT0163 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $4,100 | $4,110 | Implemented |
TT0163 # 01 Y:2015 | 01 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,742 | $5,000 | Not Implemented |
TT0163 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,611 | $3,000 | Implemented |
TT0163 # 06 Y:2015 | 06 | 2015 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,532 | $3,013 | Implemented |
TT0163 # 04 Y:2015 | 04 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,251 | $75 | Implemented |
TT0163 # 03 Y:2015 | 03 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,380 | $1,075 | Implemented |
TT0163 # 07 Y:2015 | 07 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $423 | $1,500 | Implemented |
OK0922 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,502 | $30,324 | Implemented |
OK0922 # 05 Y:2015 | 05 | 2015 | USE RADIANT HEATER FOR SPOT HEATING | $2,132 | $6,660 | Not Implemented |
OK0922 # 01 Y:2015 | 01 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $950 | $580 | Not Implemented |