Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,058
matching recommendationsNAICS | 33231 | Plate Work and Fabricated Structural Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0195 # 05 Y:2004 | 05 | 2004 | OPTIMIZE PLANT POWER FACTOR | $1,111 | $3,200 | Implemented |
LL0195 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $455 | $350 | Implemented |
LL0195 # 07 Y:2004 | 07 | 2004 | INSTALL OCCUPANCY SENSORS | $225 | $240 | Implemented |
LL0195 # 08 Y:2004 | 08 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,500 | $60 | Implemented |
LL0195 # 09 Y:2004 | 09 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $412 | $226 | Implemented |
LE0187 # 01 Y:2004 | 01 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,829 | $10,000 | Not Implemented |
LE0187 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,995 | $500 | Implemented |
LE0187 # 03 Y:2004 | 03 | 2004 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $5,383 | $9,360 | Not Implemented |
LE0187 # 04 Y:2004 | 04 | 2004 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $4,271 | $40,064 | Not Implemented |
LE0187 # 05 Y:2004 | 05 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,975 | $15,000 | Not Implemented |
LE0187 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $921 | $500 | Implemented |
LE0187 # 07 Y:2004 | 07 | 2004 | USE SYNTHETIC LUBRICANT | $810 | $500 | Not Implemented |
WV0293 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,117 | $20,400 | Implemented |
WV0293 # 02 Y:2004 | 02 | 2004 | REDESIGN PROCESS | $12,155 | $10,080 | Not Implemented |
WV0293 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,541 | $13,500 | Implemented |
WV0293 # 04 Y:2004 | 04 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $3,874 | $1,250 | Implemented |
WV0293 # 05 Y:2004 | 05 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,283 | $300 | Not Implemented |
WV0293 # 06 Y:2004 | 06 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,232 | $4,250 | Implemented |
WV0293 # 07 Y:2004 | 07 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,353 | $100 | Not Implemented |
WV0293 # 08 Y:2004 | 08 | 2004 | INSTALL OCCUPANCY SENSORS | $1,935 | $400 | Not Implemented |
WV0293 # 09 Y:2004 | 09 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,889 | $210 | Implemented |
WV0293 # 10 Y:2004 | 10 | 2004 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,815 | $3,000 | Not Implemented |
WV0293 # 11 Y:2004 | 11 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,657 | $300 | Implemented |
WV0293 # 12 Y:2004 | 12 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $565 | $1,100 | Not Implemented |
WV0293 # 13 Y:2004 | 13 | 2004 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $38,480 | $1,900 | Not Implemented |