Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
228
matching recommendationsNAICS | 332313 | Plate Work Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0316 # 09 Y:2021 | 09 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $9,528 | $625 | Not Implemented |
AM0800 # 03 Y:2020 | 03 | 2020 | PAY UTILITY BILLS ON TIME | $2,148 | $0 | Implemented |
AM0800 # 06 Y:2020 | 06 | 2020 | USE SYNTHETIC LUBRICANT | $395 | $150 | Implemented |
AM0800 # 04 Y:2020 | 04 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,700 | $267 | Implemented |
AM0800 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,960 | $2,460 | Implemented |
AM0800 # 01 Y:2020 | 01 | 2020 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $487,100 | $3,000 | Implemented |
AM0800 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,540 | $40 | Implemented |
LS1913 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $989 | $225 | Not Implemented |
LS1913 # 06 Y:2019 | 06 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $65 | $193 | Not Implemented |
LS1913 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,611 | $8,430 | Not Implemented |
LS1913 # 03 Y:2019 | 03 | 2019 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $3,051 | $270 | Not Implemented |
LS1913 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $402 | $25 | Not Implemented |
LS1913 # 01 Y:2019 | 01 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,175 | $50 | Not Implemented |
AM0773 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13 | $10 | Implemented |
AM0773 # 01 Y:2019 | 01 | 2019 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $17,060 | $25,000 | Not Implemented |
AM0773 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,552 | $12,220 | Not Implemented |
AM0773 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,768 | $1,000 | Implemented |
AM0773 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,077 | $480 | Implemented |
AM0773 # 06 Y:2019 | 06 | 2019 | USE SYNTHETIC LUBRICANT | $92 | $40 | Not Implemented |
AM0773 # 07 Y:2019 | 07 | 2019 | PAY UTILITY BILLS ON TIME | $1,751 | $0 | Not Implemented |
AM0773 # 08 Y:2019 | 08 | 2019 | OPTIMIZE PLANT POWER FACTOR | $6,464 | $18,747 | Not Implemented |
UK1806 # 03 Y:2018 | 03 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,312 | $1,100 | n/a |
UK1806 # 04 Y:2018 | 04 | 2018 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $17,440 | $18,575 | n/a |
UK1806 # 02 Y:2018 | 02 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,221 | $0 | n/a |
UK1806 # 01 Y:2018 | 01 | 2018 | UPGRADE CONTROLS ON COMPRESSORS | $10,567 | $9,500 | n/a |