Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsNAICS | 332431 | Metal Can Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0509 # 09 Y:2015 | 09 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $553 | $634 | Implemented |
WV0509 # 08 Y:2015 | 08 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $599 | $182 | Implemented |
WV0509 # 07 Y:2015 | 07 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $860 | $39 | Not Implemented |
WV0509 # 06 Y:2015 | 06 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,057 | $4,884 | Implemented |
WV0509 # 05 Y:2015 | 05 | 2015 | INSULATE BARE EQUIPMENT | $2,835 | $885 | Implemented |
WV0509 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,146 | $3,449 | Implemented |
WV0509 # 03 Y:2015 | 03 | 2015 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $6,021 | $1,000 | Implemented |
WV0509 # 02 Y:2015 | 02 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,331 | $0 | Not Implemented |
WV0509 # 01 Y:2015 | 01 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $227,708 | $366,480 | Not Implemented |
WV0480 # 06 Y:2014 | 06 | 2014 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,967 | $1,000 | Implemented |
WV0480 # 12 Y:2014 | 12 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $783 | $396 | Implemented |
WV0480 # 11 Y:2014 | 11 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $934 | $1,078 | Implemented |
WV0480 # 10 Y:2014 | 10 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,088 | $500 | Implemented |
WV0480 # 09 Y:2014 | 09 | 2014 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,181 | $2,188 | Not Implemented |
WV0480 # 08 Y:2014 | 08 | 2014 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $2,520 | $894 | Not Implemented |
WV0480 # 07 Y:2014 | 07 | 2014 | OPTIMIZE PLANT POWER FACTOR | $2,869 | $13,803 | Not Implemented |
WV0480 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,543 | $3,291 | Implemented |
WV0480 # 04 Y:2014 | 04 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,140 | $2,788 | Not Implemented |
WV0480 # 03 Y:2014 | 03 | 2014 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,929 | $2,475 | Not Implemented |
WV0480 # 02 Y:2014 | 02 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,078 | $11,520 | Not Implemented |
WV0480 # 01 Y:2014 | 01 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,022 | $11,662 | Implemented |
WV0359 # 01 Y:2007 | 01 | 2007 | USE RADIANT HEATER FOR SPOT HEATING | $23,898 | $37,000 | Not Implemented |
WV0359 # 11 Y:2007 | 11 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $538 | $131 | Implemented |
WV0359 # 10 Y:2007 | 10 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,313 | $850 | Implemented |
WV0359 # 09 Y:2007 | 09 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,391 | $0 | Implemented |