IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

648

matching recommendations
Reset
NAICS 33271 Machine Shops
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0403 # 06 Y:2015 06 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $596 $600 Not Implemented
LE0403 # 07 Y:2015 07 2015 INSTALL TIMERS AND/OR THERMOSTATS $522 $625 Not Implemented
LE0403 # 08 Y:2015 08 2015 INSTALL OCCUPANCY SENSORS $876 $1,943 Implemented
LE0403 # 09 Y:2015 09 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,928 $5,333 Not Implemented
LE0403 # 10 Y:2015 10 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $990 $3,075 Not Implemented
LE0403 # 11 Y:2015 11 2015 RECOVER WASTE HEAT FROM EQUIPMENT $489 $1,750 Not Implemented
LE0403 # 12 Y:2015 12 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $120 $612 Not Implemented
CO0711 # 01 Y:2015 01 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,360 $620 n/a
CO0711 # 02 Y:2015 02 2015 INSULATE BARE EQUIPMENT $900 $960 n/a
CO0711 # 03 Y:2015 03 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $350 $340 n/a
CO0711 # 04 Y:2015 04 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,960 $15,540 n/a
BD0460 # 01 Y:2015 01 2015 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $1,989 $2,500 Not Implemented
BD0460 # 02 Y:2015 02 2015 INSTALL OCCUPANCY SENSORS $2,713 $750 Not Implemented
BD0460 # 03 Y:2015 03 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,753 $500 Implemented
BD0460 # 04 Y:2015 04 2015 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $741 $20 Implemented
BD0460 # 05 Y:2015 05 2015 USE PHOTOCELL CONTROLS $1,240 $375 Not Implemented
BD0460 # 06 Y:2015 06 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $263 $25 Implemented
BD0460 # 07 Y:2015 07 2015 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $505 $500 Implemented
BD0460 # 08 Y:2015 08 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $350 $275 Not Implemented
BS0054 # 01 Y:2015 01 2015 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $741 $1,255 Not Implemented
BS0054 # 02 Y:2015 02 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $29 $45 Implemented
BS0054 # 03 Y:2015 03 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $597 $4,830 Implemented
BS0054 # 04 Y:2015 04 2015 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $268 $9 Not Implemented
BS0054 # 05 Y:2015 05 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $75 $374 Implemented
BS0054 # 06 Y:2015 06 2015 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $5,375 $50,351 Not Implemented