Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
57
matching recommendationsNAICS | 3328 | Coating, Engraving, Heat Treating, and Allied Activities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1515 # 13 Y:2015 | 13 | 2015 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $976 | $854 | Implemented |
UK1515 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,105 | $1,169 | Implemented |
UK1515 # 03 Y:2015 | 03 | 2015 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $597 | $0 | Implemented |
UK1515 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,141 | $3,760 | Implemented |
UK1515 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,346 | $11,375 | Implemented |
UK1515 # 05 Y:2015 | 05 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,215 | $0 | Implemented |
UK1515 # 06 Y:2015 | 06 | 2015 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $426 | $0 | Not Implemented |
UK1515 # 08 Y:2015 | 08 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,702 | $1,700 | Implemented |
UK1515 # 09 Y:2015 | 09 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $15,940 | $12,750 | Not Implemented |
UK1515 # 07 Y:2015 | 07 | 2015 | CLEAN CONDENSER TUBES | $575 | $500 | Implemented |
UK1515 # 14 Y:2015 | 14 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $10,160 | $5,539 | Implemented |
UK1515 # 11 Y:2015 | 11 | 2015 | ELIMINATE/REDUCE AN OPERATION | $144,648 | $0 | Implemented |
UK1515 # 12 Y:2015 | 12 | 2015 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $4,162 | $4,332 | Not Implemented |
UK1515 # 10 Y:2015 | 10 | 2015 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $838 | $0 | Implemented |
WV0515 # 02 Y:2015 | 02 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,569 | $1,700 | Implemented |
WV0515 # 07 Y:2015 | 07 | 2015 | INSTALL SET-BACK TIMERS | $1,310 | $1,175 | Implemented |
WV0515 # 09 Y:2015 | 09 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $181 | $35 | Implemented |
WV0515 # 06 Y:2015 | 06 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,694 | $6,400 | Not Implemented |
WV0515 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $1,835 | $920 | Implemented |
WV0515 # 08 Y:2015 | 08 | 2015 | INSTALL OCCUPANCY SENSORS | $975 | $3,180 | Implemented |
WV0515 # 04 Y:2015 | 04 | 2015 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $4,181 | $11,220 | Not Implemented |
WV0515 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $4,682 | $1,278 | Implemented |
WV0515 # 01 Y:2015 | 01 | 2015 | INSULATE FEEDWATER TANK | $13,405 | $6,253 | Not Implemented |
UA0146 # 01 Y:2015 | 01 | 2015 | AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED | $47,379 | $42,596 | Not Implemented |
UA0146 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,612 | $800 | Implemented |