28
matching recommendationsNAICS | 332813 | Electroplating, Plating, Polishing, Anodizing, and Coloring |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0227 # 05 Y:2019 | 05 | 2019 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $7,871 | $28,000 | Not Implemented |
IC0227 # 04 Y:2019 | 04 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,978 | $9,600 | Not Implemented |
IC0227 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,117 | $7,146 | Not Implemented |
IC0227 # 02 Y:2019 | 02 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,441 | $1,500 | Not Implemented |
IC0227 # 01 Y:2019 | 01 | 2019 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $3,221 | $800 | Not Implemented |
IC0226 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $919 | $689 | Not Implemented |
IC0226 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,608 | $4,300 | Not Implemented |
IC0226 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,094 | $167 | Not Implemented |
IC0226 # 04 Y:2019 | 04 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $343 | $1,200 | Not Implemented |
IC0226 # 05 Y:2019 | 05 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,367 | $0 | Not Implemented |
IC0226 # 06 Y:2019 | 06 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $650 | $60 | Not Implemented |
IP0123 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $442 | $70 | Implemented |
IP0123 # 10 Y:2019 | 10 | 2019 | INSULATE BARE EQUIPMENT | $153 | $692 | Not Implemented |
IP0123 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $503 | $100 | Not Implemented |
IP0123 # 05 Y:2019 | 05 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,980 | $440 | Implemented |
IP0123 # 06 Y:2019 | 06 | 2019 | OPTIMIZE PLANT POWER FACTOR | $5,541 | $9,685 | Not Implemented |
IP0123 # 07 Y:2019 | 07 | 2019 | INSULATE BARE EQUIPMENT | $96 | $200 | Not Implemented |
IP0123 # 08 Y:2019 | 08 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $758 | $2,290 | Implemented |
IP0123 # 09 Y:2019 | 09 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,165 | $13,663 | Implemented |
IP0123 # 02 Y:2019 | 02 | 2019 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $248 | $0 | Implemented |
IP0123 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $286 | $7 | Implemented |
AM0771 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $240 | $350 | Not Implemented |
AM0771 # 06 Y:2019 | 06 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $300 | $26 | Implemented |
AM0771 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $950 | $0 | Not Implemented |
AM0771 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,500 | $1,340 | Implemented |