Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
762
matching recommendationsNAICS | 33291 | Metal Valve Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0758 # 02 Y:2008 | 02 | 2008 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $1,470 | $6,841 | Not Implemented |
OK0758 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,699 | $51,819 | Implemented |
OK0758 # 04 Y:2008 | 04 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $215 | $1,762 | Not Implemented |
OK0758 # 05 Y:2008 | 05 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,290 | $1,000 | Implemented |
OK0758 # 06 Y:2008 | 06 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $144 | $754 | Not Implemented |
OK0758 # 07 Y:2008 | 07 | 2008 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,316 | $600 | Implemented |
SD0394 # 01 Y:2007 | 01 | 2007 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $72,155 | $103,750 | Not Implemented |
SD0394 # 02 Y:2007 | 02 | 2007 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $33,374 | $226,540 | Not Implemented |
SD0394 # 03 Y:2007 | 03 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,868 | $3,046 | Not Implemented |
SD0394 # 04 Y:2007 | 04 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,578 | $0 | Not Implemented |
SD0394 # 05 Y:2007 | 05 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $302 | $200 | Not Implemented |
MS0304 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $289,291 | $222,009 | Implemented |
MS0304 # 02 Y:2006 | 02 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $118,243 | $1,820 | Implemented |
MS0304 # 03 Y:2006 | 03 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,366 | $16,063 | Implemented |
MS0304 # 04 Y:2006 | 04 | 2006 | USE SYNTHETIC LUBRICANT | $7,010 | $153 | Implemented |
LE0242 # 01 Y:2006 | 01 | 2006 | USE SOLAR HEAT TO MAKE ELECTRICTY | $734,219 | $1,251,036 | Implemented |
LE0242 # 02 Y:2006 | 02 | 2006 | INSTALL TIMERS AND/OR THERMOSTATS | $22,987 | $20,000 | Implemented |
LE0242 # 03 Y:2006 | 03 | 2006 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $7,219 | $960 | Implemented |
LE0242 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,843 | $1,000 | Implemented |
LE0242 # 05 Y:2006 | 05 | 2006 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,240 | $6,400 | Implemented |
LE0242 # 06 Y:2006 | 06 | 2006 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,001 | $2,000 | Implemented |
LE0242 # 07 Y:2006 | 07 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $996 | $1,000 | Implemented |
LE0242 # 08 Y:2006 | 08 | 2006 | INSTALL OCCUPANCY SENSORS | $152 | $75 | Implemented |
LE0242 # 09 Y:2006 | 09 | 2006 | INSTALL OCCUPANCY SENSORS | $651 | $450 | Not Implemented |
LE0242 # 10 Y:2006 | 10 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,990 | $8,750 | Implemented |