Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
897
matching recommendationsNAICS | 332999 | All Other Miscellaneous Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0782 # 02 Y:2009 | 02 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,732 | $3,742 | Not Implemented |
OK0782 # 03 Y:2009 | 03 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,733 | $0 | Implemented |
OK0782 # 04 Y:2009 | 04 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,005 | $7,542 | Not Implemented |
OK0782 # 05 Y:2009 | 05 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,300 | $11,120 | Not Implemented |
OK0782 # 06 Y:2009 | 06 | 2009 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $804 | $4,800 | Not Implemented |
OK0782 # 07 Y:2009 | 07 | 2009 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,815 | $820 | Implemented |
OK0782 # 08 Y:2009 | 08 | 2009 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $700 | $1,825 | Implemented |
UW0032 # 01 Y:2009 | 01 | 2009 | INSULATE BARE EQUIPMENT | $8,800 | $7,248 | Not Implemented |
UW0032 # 02 Y:2009 | 02 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,782 | $31,747 | Implemented |
UW0032 # 03 Y:2009 | 03 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,643 | $10,000 | Implemented |
UW0032 # 04 Y:2009 | 04 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,065 | $3,070 | Implemented |
UW0032 # 05 Y:2009 | 05 | 2009 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $297 | $200 | Implemented |
UD0802 # 01 Y:2009 | 01 | 2009 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $13,072 | $16,185 | Not Implemented |
UD0802 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,384 | $29,087 | Implemented |
UD0802 # 03 Y:2009 | 03 | 2009 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,645 | $0 | Implemented |
UD0802 # 04 Y:2009 | 04 | 2009 | INSTALL AUTOMATIC STACK DAMPER | $3,637 | $1,000 | Not Implemented |
UD0802 # 05 Y:2009 | 05 | 2009 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,711 | $6,468 | Not Implemented |
UD0802 # 06 Y:2009 | 06 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,230 | $1,500 | Implemented |
UD0802 # 07 Y:2009 | 07 | 2009 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $1,084 | $2,812 | Not Implemented |
UD0802 # 08 Y:2009 | 08 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $797 | $1,907 | Implemented |
UD0802 # 09 Y:2009 | 09 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $487 | $2,374 | Implemented |
UD0802 # 10 Y:2009 | 10 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,334 | $1,000 | Implemented |
UD0802 # 11 Y:2009 | 11 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $194 | $0 | Not Implemented |
LL0312 # 01 Y:2009 | 01 | 2009 | INSULATE BARE EQUIPMENT | $8,673 | $10,644 | Implemented |
LL0312 # 02 Y:2009 | 02 | 2009 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,439 | $1,680 | Implemented |