Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
198
matching recommendationsNAICS | 333 | Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0630 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,850 | $9,294 | Implemented |
SD0630 # 08 Y:2023 | 08 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,832 | $1,080 | Implemented |
SD0630 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $664 | $1,500 | Implemented |
SD0630 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $598 | $500 | Implemented |
SD0630 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,064 | $7,542 | Implemented |
SF0561 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,435 | $3,959 | Not Implemented |
SF0561 # 03 Y:2020 | 03 | 2020 | INSULATE BARE EQUIPMENT | $3,116 | $1,412 | Implemented |
SF0561 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,548 | $4,226 | Implemented |
SF0561 # 06 Y:2020 | 06 | 2020 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,263 | $18,437 | Not Implemented |
SF0561 # 01 Y:2020 | 01 | 2020 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,397 | $525 | Not Implemented |
SF0561 # 07 Y:2020 | 07 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $35,550 | $236,909 | Implemented |
SF0561 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,203 | $110 | Not Implemented |
SD0574 # 03 Y:2019 | 03 | 2019 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $485 | $1,290 | Not Implemented |
SD0574 # 05 Y:2019 | 05 | 2019 | REDUCE SCRAP PRODUCTION | $25,514 | $1,500 | Implemented |
SD0574 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,259 | $0 | Implemented |
SD0574 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $886 | $300 | Implemented |
SD0574 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $332 | $0 | Not Implemented |
SD0551 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $433 | $1,500 | Implemented |
SD0551 # 01 Y:2017 | 01 | 2017 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $20,950 | $86,400 | Not Implemented |
SD0551 # 03 Y:2017 | 03 | 2017 | INSTALL OCCUPANCY SENSORS | $899 | $3,000 | Implemented |
SD0551 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,959 | $35,776 | Implemented |
SD0551 # 05 Y:2017 | 05 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $169 | $200 | Implemented |
SF0499 # 04 Y:2017 | 04 | 2017 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $18,778 | $30,000 | Implemented |
SF0499 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,955 | $0 | Implemented |
SF0499 # 03 Y:2017 | 03 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $600 | $0 | Not Implemented |