IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

292

matching recommendations
Reset
NAICS 333 Machinery Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1009 # 05 Y:2019 05 2019 OPTIMIZE PLANT POWER FACTOR $365 $1,365 Not Implemented
OK1009 # 04 Y:2019 04 2019 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $7,915 $0 Implemented
OK1009 # 07 Y:2019 07 2019 INSTALL TIMERS AND/OR THERMOSTATS $8,182 $1,430 Implemented
OK1007 # 05 Y:2019 05 2019 INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM $96,866 $35,244 Not Implemented
OK1007 # 04 Y:2019 04 2019 OPTIMIZE PLANT POWER FACTOR $2,995 $1,980 Not Implemented
OK1007 # 03 Y:2019 03 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $9,238 $0 Not Implemented
OK1007 # 02 Y:2019 02 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $390 $1,047 Not Implemented
OK1007 # 01 Y:2019 01 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,929 $3,017 Not Implemented
OK0966 # 09 Y:2017 09 2017 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $36 $100 Implemented
OK0966 # 08 Y:2017 08 2017 COVER OPEN TANKS $2,956 $1,250 Not Implemented
OK0966 # 07 Y:2017 07 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,676 $17,550 Implemented
OK0966 # 06 Y:2017 06 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,570 $17,250 Implemented
OK0966 # 05 Y:2017 05 2017 TURN OFF EQUIPMENT WHEN NOT IN USE $7,886 $0 Not Implemented
OK0966 # 04 Y:2017 04 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,526 $21,137 Implemented
OK0966 # 03 Y:2017 03 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $74,450 $305,694 Implemented
OK0966 # 02 Y:2017 02 2017 BASE UTILITY CHARGES ON USAGE RATHER THAN AREA OCCUPIED $113,700 $24,000 Implemented
OK0966 # 01 Y:2017 01 2017 REPLACE BOILER $125,000 $442,000 Not Implemented
OK0905 # 13 Y:2015 13 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,731 $8,268 Not Implemented
OK0905 # 01 Y:2015 01 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,534 $2,400 Not Implemented
OK0905 # 02 Y:2015 02 2015 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $98 $77 Not Implemented
OK0905 # 03 Y:2015 03 2015 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $146 $463 Not Implemented
OK0905 # 04 Y:2015 04 2015 RECOVER WASTE HEAT FROM EQUIPMENT $468 $1,220 Not Implemented
OK0905 # 05 Y:2015 05 2015 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $1,180 $2,817 Not Implemented
OK0905 # 06 Y:2015 06 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $920 $2,441 Not Implemented
OK0905 # 12 Y:2015 12 2015 EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME $1,749 $1,248 Not Implemented