Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
180
matching recommendationsNAICS | 3331 | Agriculture, Construction, and Mining Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2218 # 06 Y:2022 | 06 | 2022 | IMPROVE SPACE COMFORT CONDITIONING | $11,310 | $17,640 | Not Implemented |
LS2218 # 05 Y:2022 | 05 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,084 | $800 | Not Implemented |
LS2218 # 04 Y:2022 | 04 | 2022 | ELIMINATE PRACTICE OF MIXING WASTE STREAMS | $12,800 | $2,600 | Not Implemented |
LS2218 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $535 | $90 | Implemented |
LS2218 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $3,196 | $100 | Implemented |
LS2218 # 09 Y:2022 | 09 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $1,482 | $4,700 | Not Implemented |
LS2218 # 01 Y:2022 | 01 | 2022 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $21,720 | $0 | Implemented |
LS2218 # 08 Y:2022 | 08 | 2022 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $78,203 | $201,075 | Not Implemented |
LS2218 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,287 | $38,480 | Implemented |
LS2218 # 10 Y:2022 | 10 | 2022 | CONVERT TO ROBOTIC PAINTING | $37,576 | $140,000 | Not Implemented |
LS2208 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $7,289 | $200 | Implemented |
LS2208 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $651 | $50 | Not Implemented |
LS2208 # 09 Y:2022 | 09 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $15,212 | $215,340 | Not Implemented |
LS2208 # 01 Y:2022 | 01 | 2022 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $378 | $10 | Not Implemented |
LS2208 # 06 Y:2022 | 06 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,660 | $2,800 | Not Implemented |
LS2208 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,527 | $450 | Implemented |
LS2208 # 07 Y:2022 | 07 | 2022 | INSTALL OCCUPANCY SENSORS | $304 | $114 | Not Implemented |
LS2208 # 05 Y:2022 | 05 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $975 | $240 | Not Implemented |
LS2208 # 08 Y:2022 | 08 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,440 | $14,643 | Implemented |
LS1901 # 05 Y:2019 | 05 | 2019 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $45,500 | $27,000 | Not Implemented |
LS1901 # 03 Y:2019 | 03 | 2019 | INSTALL OCCUPANCY SENSORS | $483 | $75 | Not Implemented |
LS1901 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,246 | $21,652 | Not Implemented |
LS1901 # 04 Y:2019 | 04 | 2019 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $1,150 | $100 | Implemented |
LS1901 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $1,421 | $50 | Implemented |
LS1901 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $374 | $25 | Not Implemented |