Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26
matching recommendationsNAICS | 3331 | Agriculture, Construction, and Mining Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0008 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22 | $23 | Implemented |
MZ0008 # 05 Y:2007 | 05 | 2007 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $812 | $0 | Implemented |
MZ0008 # 04 Y:2007 | 04 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $694 | $1,300 | Implemented |
MZ0008 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,289 | $800 | Implemented |
MZ0008 # 02 Y:2007 | 02 | 2007 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $44,772 | $6,399 | Implemented |
MZ0008 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,856 | $21,050 | Implemented |
UD0765 # 02 Y:2007 | 02 | 2007 | USE SOLAR HEAT TO HEAT MAKE-UP AIR | $4,626 | $17,500 | Not Implemented |
UD0765 # 13 Y:2007 | 13 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $216 | $324 | Implemented |
UD0765 # 12 Y:2007 | 12 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $233 | $500 | Implemented |
UD0765 # 11 Y:2007 | 11 | 2007 | INSTALL SKYLIGHTS | $354 | $1,083 | Implemented |
UD0765 # 10 Y:2007 | 10 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $496 | $0 | Implemented |
UD0765 # 09 Y:2007 | 09 | 2007 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $500 | $0 | Implemented |
UD0765 # 08 Y:2007 | 08 | 2007 | INSTALL SKYLIGHTS | $666 | $2,421 | Implemented |
UD0765 # 07 Y:2007 | 07 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $764 | $883 | Implemented |
UD0765 # 06 Y:2007 | 06 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $997 | $0 | Implemented |
UD0765 # 05 Y:2007 | 05 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,628 | $915 | Implemented |
UD0765 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,808 | $3,777 | Implemented |
UD0765 # 03 Y:2007 | 03 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,922 | $7,945 | Implemented |
UD0765 # 01 Y:2007 | 01 | 2007 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $9,128 | $3,450 | Implemented |
AM0530 # 01 Y:2007 | 01 | 2007 | PURCHASE APPROPRIATELY SIZED MATERIAL | $13,025 | $500 | Not Implemented |
AM0530 # 02 Y:2007 | 02 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,000 | $38,913 | Implemented |
AM0530 # 03 Y:2007 | 03 | 2007 | KEEP LAMPS AND REFLECTORS CLEAN | $880 | $0 | Implemented |
AM0530 # 04 Y:2007 | 04 | 2007 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $670 | $0 | Implemented |
AM0530 # 05 Y:2007 | 05 | 2007 | USE PHOTOCELL CONTROLS | $620 | $45 | Implemented |
AM0530 # 06 Y:2007 | 06 | 2007 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $430 | $0 | Implemented |