Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
540
matching recommendationsNAICS | 33313 | Mining and Oil and Gas Field Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0630 # 01 Y:2022 | 01 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $11,322 | $44,160 | Not Implemented |
WV0630 # 04 Y:2022 | 04 | 2022 | MINIMIZE WATER USAGE | $706 | $2,559 | Implemented |
WV0630 # 05 Y:2022 | 05 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $405 | $1,431 | Implemented |
WV0630 # 06 Y:2022 | 06 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $371 | $911 | Implemented |
WV0630 # 07 Y:2022 | 07 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $305 | $510 | Implemented |
WV0630 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $2,677 | $7,291 | Implemented |
OK1068 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,325 | $5,412 | Implemented |
OK1068 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,103 | $0 | Implemented |
OK1068 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,561 | $18,463 | Not Implemented |
OK1068 # 03 Y:2022 | 03 | 2022 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $5,553 | $3,192 | Implemented |
OK1068 # 05 Y:2022 | 05 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $830 | $0 | Not Implemented |
OK1068 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,141 | $1,208 | Implemented |
LS2208 # 08 Y:2022 | 08 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,440 | $14,643 | Implemented |
LS2208 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $7,289 | $200 | Implemented |
LS2208 # 05 Y:2022 | 05 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $975 | $240 | Not Implemented |
LS2208 # 07 Y:2022 | 07 | 2022 | INSTALL OCCUPANCY SENSORS | $304 | $114 | Not Implemented |
LS2208 # 09 Y:2022 | 09 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $15,212 | $215,340 | Not Implemented |
LS2208 # 06 Y:2022 | 06 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,660 | $2,800 | Not Implemented |
LS2208 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $651 | $50 | Not Implemented |
LS2208 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,527 | $450 | Implemented |
LS2208 # 01 Y:2022 | 01 | 2022 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $378 | $10 | Not Implemented |
OK1064 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,414 | $774 | Implemented |
OK1064 # 03 Y:2022 | 03 | 2022 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $367 | $700 | Implemented |
OK1064 # 01 Y:2022 | 01 | 2022 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $9,509 | $2,061 | Not Implemented |
OK1064 # 02 Y:2022 | 02 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,321 | $22,000 | Implemented |