IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

72

matching recommendations
Reset
NAICS 33313 Mining and Oil and Gas Field Machinery Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0895 # 01 Y:2014 01 2014 RECOVER WASTE HEAT FROM EQUIPMENT $829 $689 Not Implemented
OK0895 # 02 Y:2014 02 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $383 $678 Not Implemented
OK0895 # 03 Y:2014 03 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $706 $1,400 Implemented
OK0895 # 04 Y:2014 04 2014 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $669 $1,452 Implemented
OK0895 # 05 Y:2014 05 2014 USE PHOTOCELL CONTROLS $16,923 $24,600 Not Implemented
OK0895 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,754 $5,850 Not Implemented
OK0895 # 07 Y:2014 07 2014 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $15,028 $32,400 Not Implemented
OK0895 # 08 Y:2014 08 2014 INSULATE BARE EQUIPMENT $16,794 $3,436 Not Implemented
OK0895 # 10 Y:2014 10 2014 INSULATE BARE EQUIPMENT $9,518 $5,258 Not Implemented
OK0895 # 11 Y:2014 11 2014 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $182 $158 Not Implemented
OK0895 # 12 Y:2014 12 2014 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $4,033 $14,580 Not Implemented
OK0895 # 13 Y:2014 13 2014 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,006 $0 Not Implemented
OK0678 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,075 $823 Implemented
OK0678 # 10 Y:2004 10 2004 CONTRACT A WOOD PALLET RECYCLING COMPANY $2,985 $0 Not Implemented
OK0678 # 09 Y:2004 09 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $546 $1,154 Implemented
OK0678 # 08 Y:2004 08 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,847 $14,078 Not Implemented
OK0678 # 07 Y:2004 07 2004 INSTALL SET-BACK TIMERS $3,347 $2,200 Implemented
OK0678 # 06 Y:2004 06 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $5,188 $12,597 Not Implemented
OK0678 # 05 Y:2004 05 2004 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $22,602 $28,350 Not Implemented
OK0678 # 04 Y:2004 04 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $13,162 $800 Implemented
OK0678 # 03 Y:2004 03 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,836 $10,835 Implemented
OK0678 # 02 Y:2004 02 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,817 $3,690 Implemented