Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26
matching recommendationsNAICS | 33361 | Engine, Turbine, and Power Transmission Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1070 # 02 Y:2022 | 02 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,329 | $0 | Implemented |
OK1070 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,014 | $990 | Implemented |
OK1070 # 04 Y:2022 | 04 | 2022 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $3,689 | $3,294 | Not Implemented |
OK1070 # 05 Y:2022 | 05 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $2,659 | $8,954 | Implemented |
OK1070 # 06 Y:2022 | 06 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,927 | $3,985 | Not Implemented |
OK1070 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,761 | $4,884 | Not Implemented |
OK1070 # 08 Y:2022 | 08 | 2022 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $2,533 | $440 | Not Implemented |
OK1070 # 01 Y:2022 | 01 | 2022 | OPTIMIZE PLANT POWER FACTOR | $2,809 | $9,600 | Not Implemented |
OK1023 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,874 | $15,402 | Not Implemented |
OK1023 # 05 Y:2020 | 05 | 2020 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $415 | $538 | Not Implemented |
OK1023 # 04 Y:2020 | 04 | 2020 | USE RADIANT HEATER FOR SPOT HEATING | $915 | $3,252 | Not Implemented |
OK1023 # 03 Y:2020 | 03 | 2020 | OPTIMIZE PLANT POWER FACTOR | $464 | $1,236 | Not Implemented |
OK1023 # 02 Y:2020 | 02 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,606 | $4,736 | Not Implemented |
OK1023 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $770 | $0 | Not Implemented |
OK0816 # 07 Y:2011 | 07 | 2011 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $17,005 | $315,900 | Not Implemented |
OK0816 # 08 Y:2011 | 08 | 2011 | REPLACE BOILER | $26,135 | $24,220 | Implemented |
OK0816 # 09 Y:2011 | 09 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,244 | $11,700 | Not Implemented |
OK0816 # 10 Y:2011 | 10 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,037 | $0 | Implemented |
OK0816 # 11 Y:2011 | 11 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,760 | $1,338 | Implemented |
OK0816 # 12 Y:2011 | 12 | 2011 | INSULATE BARE EQUIPMENT | $1,893 | $2,263 | Not Implemented |
OK0816 # 06 Y:2011 | 06 | 2011 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $13,197 | $9,150 | Not Implemented |
OK0816 # 05 Y:2011 | 05 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $17,462 | $0 | Not Implemented |
OK0816 # 04 Y:2011 | 04 | 2011 | DISCONNECT BALLASTS | $481 | $921 | Not Implemented |
OK0816 # 03 Y:2011 | 03 | 2011 | INSTALL OCCUPANCY SENSORS | $391 | $456 | Implemented |
OK0816 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $245 | $1,488 | Implemented |