Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,149
matching recommendationsNAICS | 334 | Computer and Electronic Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0421 # 08 Y:2023 | 08 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,009 | $0 | Implemented |
MI0421 # 05 Y:2023 | 05 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $49,124 | $120 | Implemented |
MI0421 # 09 Y:2023 | 09 | 2023 | INSTALL OCCUPANCY SENSORS | $2,695 | $1,365 | Implemented |
MI0421 # 07 Y:2023 | 07 | 2023 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $11,466 | $1,492 | Implemented |
DL0220 # 02 Y:2023 | 02 | 2023 | USE OPTIMUM TEMPERATURE | $6,980 | $0 | Implemented |
DL0220 # 01 Y:2023 | 01 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $84,324 | $0 | Implemented |
DL0220 # 12 Y:2023 | 12 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,150 | $8,994 | Implemented |
MA0854 # 06 Y:2023 | 06 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,399 | $3,125 | Implemented |
MA0854 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,825 | $12,405 | Implemented |
MA0854 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $3,953 | $6,018 | Implemented |
UU0215 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,565 | $1,563 | Implemented |
UU0215 # 02 Y:2023 | 02 | 2023 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $4,878 | $48,510 | Implemented |
UU0215 # 04 Y:2023 | 04 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $5,775 | $52,882 | Implemented |
UU0215 # 07 Y:2023 | 07 | 2023 | REDESIGN PROCESS | $913 | $2,360 | Implemented |
UU0215 # 08 Y:2023 | 08 | 2023 | INSULATE BARE EQUIPMENT | $228 | $1,725 | Implemented |
UU0215 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,368 | $27,177 | Implemented |
UU0215 # 05 Y:2023 | 05 | 2023 | OPTIMIZE PLANT POWER FACTOR | $3,212 | $5,850 | Implemented |
DL0217 # 02 Y:2023 | 02 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,621 | $0 | Implemented |
DL0217 # 08 Y:2023 | 08 | 2023 | REDUCE VENTILATION AIR | $1,715 | $750 | Implemented |
DL0217 # 04 Y:2023 | 04 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $7,120 | $0 | Implemented |
DL0217 # 06 Y:2023 | 06 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $30,600 | $0 | Implemented |
DL0217 # 05 Y:2023 | 05 | 2023 | REDUCE VENTILATION AIR | $29,580 | $0 | Implemented |
DL0217 # 01 Y:2023 | 01 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $14,180 | $0 | Implemented |
DL0217 # 11 Y:2023 | 11 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,318 | $4,100 | Implemented |
DL0217 # 07 Y:2023 | 07 | 2023 | REDUCE VENTILATION AIR | $2,650 | $0 | Implemented |