Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
297
matching recommendationsNAICS | 334 | Computer and Electronic Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0029 # 06 Y:2025 | 06 | 2025 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $10,952 | $0 | n/a |
SJ0029 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $137,645 | $376,457 | n/a |
SJ0029 # 03 Y:2025 | 03 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $78 | $0 | n/a |
SJ0029 # 05 Y:2025 | 05 | 2025 | INSULATE BARE EQUIPMENT | $378 | $574 | n/a |
SJ0029 # 02 Y:2025 | 02 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,400 | $1,940 | n/a |
SJ0029 # 04 Y:2025 | 04 | 2025 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,874 | $6,782 | n/a |
SD0656 # 11 Y:2024 | 11 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,784 | $2,109 | n/a |
SD0656 # 05 Y:2024 | 05 | 2024 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $2,144 | $2,200 | n/a |
SD0656 # 01 Y:2024 | 01 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,203 | $18,032 | n/a |
SD0656 # 04 Y:2024 | 04 | 2024 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $54,151 | $15,130 | n/a |
SD0656 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,164 | $2,109 | n/a |
SD0656 # 02 Y:2024 | 02 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $49,836 | $74,485 | n/a |
SD0656 # 09 Y:2024 | 09 | 2024 | PREVENT EXCESSIVE SOLVENT USAGE (OPERATOR TRAINING) | $35,678 | $51,900 | n/a |
SD0656 # 03 Y:2024 | 03 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $54,943 | $3,087 | n/a |
SD0656 # 07 Y:2024 | 07 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,422 | $2,040 | n/a |
SD0656 # 10 Y:2024 | 10 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,299 | $3,896 | n/a |
SD0656 # 08 Y:2024 | 08 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,188 | $500 | n/a |
SD0656 # 12 Y:2024 | 12 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,042 | $11,447 | n/a |
SD0650 # 04 Y:2024 | 04 | 2024 | USE PHOTOCELL CONTROLS | $2,366 | $2,165 | Implemented |
SD0650 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $786 | $1,463 | Implemented |
SD0650 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $48,985 | $0 | Not Implemented |
SD0650 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $59,676 | $88,292 | Not Implemented |
SD0644 # 01 Y:2024 | 01 | 2024 | USE PHOTOCELL CONTROLS | $693 | $1,890 | Not Implemented |
SD0644 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $189 | $240 | Not Implemented |
SD0644 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $595 | $1,016 | Not Implemented |