Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
291
matching recommendationsNAICS | 334 | Computer and Electronic Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0656 # 11 Y:2024 | 11 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,784 | $2,109 | n/a |
SD0656 # 05 Y:2024 | 05 | 2024 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $2,144 | $2,200 | n/a |
SD0656 # 02 Y:2024 | 02 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $49,836 | $74,485 | n/a |
SD0656 # 03 Y:2024 | 03 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $54,943 | $3,087 | n/a |
SD0656 # 04 Y:2024 | 04 | 2024 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $54,151 | $15,130 | n/a |
SD0656 # 09 Y:2024 | 09 | 2024 | PREVENT EXCESSIVE SOLVENT USAGE (OPERATOR TRAINING) | $35,678 | $51,900 | n/a |
SD0656 # 08 Y:2024 | 08 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,188 | $500 | n/a |
SD0656 # 01 Y:2024 | 01 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,203 | $18,032 | n/a |
SD0656 # 12 Y:2024 | 12 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,042 | $11,447 | n/a |
SD0656 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,164 | $2,109 | n/a |
SD0656 # 10 Y:2024 | 10 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,299 | $3,896 | n/a |
SD0656 # 07 Y:2024 | 07 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,422 | $2,040 | n/a |
SD0650 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $59,676 | $88,292 | n/a |
SD0650 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $48,985 | $0 | n/a |
SD0650 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $786 | $1,463 | n/a |
SD0650 # 04 Y:2024 | 04 | 2024 | USE PHOTOCELL CONTROLS | $2,366 | $2,165 | n/a |
SD0644 # 07 Y:2024 | 07 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $108,342 | $141,268 | n/a |
SD0644 # 05 Y:2024 | 05 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $5,961 | $1,050 | n/a |
SD0644 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $189 | $240 | n/a |
SD0644 # 01 Y:2024 | 01 | 2024 | USE PHOTOCELL CONTROLS | $693 | $2,383 | n/a |
SD0644 # 09 Y:2024 | 09 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $738 | $3,205 | n/a |
SD0644 # 04 Y:2024 | 04 | 2024 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $3,868 | $8,200 | n/a |
SD0644 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $595 | $1,016 | n/a |
SD0644 # 06 Y:2024 | 06 | 2024 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $61,738 | $0 | n/a |
SD0644 # 08 Y:2024 | 08 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $7,472 | $0 | n/a |