Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
83
matching recommendationsNAICS | 335 | Electrical Equipment, Appliance, and Component Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0020 # 02 Y:2013 | 02 | 2013 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $804 | $1,510 | Not Implemented |
WM0020 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,644 | $813 | Implemented |
WI0517 # 07 Y:2006 | 07 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,730 | $5,500 | Not Implemented |
WI0517 # 01 Y:2006 | 01 | 2006 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $27,918 | $6,000 | Not Implemented |
WI0517 # 02 Y:2006 | 02 | 2006 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $25,159 | $4,500 | Not Implemented |
WI0517 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,406 | $37,744 | Implemented |
WI0517 # 04 Y:2006 | 04 | 2006 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $9,970 | $14,000 | Not Implemented |
WI0517 # 05 Y:2006 | 05 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,306 | $500 | Implemented |
WI0517 # 06 Y:2006 | 06 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,872 | $2,000 | Not Implemented |
WI0489 # 08 Y:2005 | 08 | 2005 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $815 | $0 | Implemented |
WI0489 # 01 Y:2005 | 01 | 2005 | INSTALL TIMERS AND/OR THERMOSTATS | $8,655 | $1,600 | Implemented |
WI0489 # 02 Y:2005 | 02 | 2005 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $6,360 | $0 | Implemented |
WI0489 # 03 Y:2005 | 03 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,677 | $758 | Implemented |
WI0489 # 04 Y:2005 | 04 | 2005 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $3,606 | $3,000 | Not Implemented |
WI0489 # 05 Y:2005 | 05 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,494 | $2,314 | Implemented |
WI0489 # 07 Y:2005 | 07 | 2005 | IMPROVE LUBRICATION PRACTICES | $735 | $828 | Not Implemented |
WI0489 # 09 Y:2005 | 09 | 2005 | INSTALL OCCUPANCY SENSORS | $481 | $100 | Implemented |
WI0489 # 10 Y:2005 | 10 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $206 | $0 | Implemented |
WI0489 # 06 Y:2005 | 06 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $782 | $0 | Implemented |
WI0462 # 04 Y:2004 | 04 | 2004 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,136 | $1,800 | Not Implemented |
WI0462 # 01 Y:2004 | 01 | 2004 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $30,420 | $36,000 | Not Implemented |
WI0462 # 02 Y:2004 | 02 | 2004 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $8,389 | $14,000 | Not Implemented |
WI0462 # 03 Y:2004 | 03 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,916 | $8,000 | Not Implemented |
WI0462 # 05 Y:2004 | 05 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,319 | $500 | Not Implemented |
WI0462 # 06 Y:2004 | 06 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $808 | $2,500 | Not Implemented |