IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,095

matching recommendations
Reset
NAICS 335 Electrical Equipment, Appliance, and Component Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0619 # 08 Y:2007 08 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,151 $7,151 Not Implemented
MA0619 # 09 Y:2007 09 2007 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $3,560 $1,184 Implemented
BD0321 # 01 Y:2007 01 2007 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $32,663 $120,000 Implemented
BD0321 # 02 Y:2007 02 2007 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $5,141 $2,400 Not Implemented
BD0321 # 03 Y:2007 03 2007 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $2,096 $10,000 Not Implemented
BD0321 # 04 Y:2007 04 2007 INSTALL OCCUPANCY SENSORS $534 $525 Not Implemented
BD0321 # 05 Y:2007 05 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $225 $0 Implemented
BD0321 # 06 Y:2007 06 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $111 $150 Not Implemented
IC0122 # 01 Y:2006 01 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $14,489 $58,358 Implemented
IC0122 # 02 Y:2006 02 2006 REPLACE BOILER $10,973 $46,865 Not Implemented
IC0122 # 03 Y:2006 03 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,130 $21,000 Not Implemented
IC0122 # 04 Y:2006 04 2006 INSTALL TIMERS AND/OR THERMOSTATS $2,700 $0 Implemented
IC0122 # 05 Y:2006 05 2006 INSTALL OCCUPANCY SENSORS $1,480 $1,791 Implemented
IC0122 # 06 Y:2006 06 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $490 $0 Implemented
IC0122 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $268 $816 Not Implemented
IC0119 # 01 Y:2006 01 2006 RECOVER AND REUSE SPENT ACID BATHS $32,160 $82,800 Not Implemented
IC0119 # 02 Y:2006 02 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,829 $600 Implemented
IC0119 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $34,559 $114,725 Implemented
IC0119 # 04 Y:2006 04 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $25,402 $61,775 Implemented
IC0119 # 05 Y:2006 05 2006 RECOVER WASTE HEAT FROM EQUIPMENT $33,836 $144,000 Not Implemented
IC0119 # 06 Y:2006 06 2006 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $130,000 $0 Not Implemented
IC0119 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,048 $38,744 Implemented
IC0119 # 08 Y:2006 08 2006 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $30,353 $312,000 Not Implemented
OK0736 # 01 Y:2006 01 2006 INSULATE BARE EQUIPMENT $224,746 $154,440 Implemented
OK0736 # 02 Y:2006 02 2006 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $447,023 $299,500 Not Implemented