Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
25
matching recommendationsNAICS | 3351 | Electric Lighting Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0821 # 06 Y:2021 | 06 | 2021 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $425 | $52 | Not Implemented |
AM0821 # 05 Y:2021 | 05 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,057 | $12 | Not Implemented |
AM0821 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,780 | $4,216 | Not Implemented |
AM0821 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,460 | $1,000 | Not Implemented |
AM0821 # 02 Y:2021 | 02 | 2021 | PAY UTILITY BILLS ON TIME | $3,204 | $0 | Not Implemented |
AM0821 # 01 Y:2021 | 01 | 2021 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $17,688 | $5,000 | Not Implemented |
AM0814 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,570 | $2,000 | Implemented |
AM0814 # 01 Y:2020 | 01 | 2020 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $74,300 | $7,400 | Implemented |
AM0814 # 03 Y:2020 | 03 | 2020 | OPTIMIZE PLANT POWER FACTOR | $6,460 | $9,830 | Not Implemented |
AM0814 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,540 | $1,000 | Implemented |
AM0814 # 05 Y:2020 | 05 | 2020 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,470 | $4,340 | Implemented |
AM0814 # 06 Y:2020 | 06 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $500 | $25 | Implemented |
AM0814 # 07 Y:2020 | 07 | 2020 | PAY UTILITY BILLS ON TIME | $490 | $0 | Implemented |
AM0814 # 08 Y:2020 | 08 | 2020 | USE SYNTHETIC LUBRICANT | $300 | $200 | Implemented |
AM0646 # 09 Y:2013 | 09 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,385 | $0 | Implemented |
AM0646 # 11 Y:2013 | 11 | 2013 | USE SYNTHETIC LUBRICANT | $215 | $0 | Implemented |
AM0646 # 10 Y:2013 | 10 | 2013 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $440 | $0 | Implemented |
AM0646 # 08 Y:2013 | 08 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,470 | $770 | Implemented |
AM0646 # 07 Y:2013 | 07 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,850 | $500 | Implemented |
AM0646 # 06 Y:2013 | 06 | 2013 | RELOCATE OVEN / FURNACE TO MORE EFFICIENT LOCATION | $2,505 | $5,010 | Not Implemented |
AM0646 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,610 | $2,250 | Implemented |
AM0646 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,470 | $2,800 | Not Implemented |
AM0646 # 03 Y:2013 | 03 | 2013 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $10,300 | $300 | Not Implemented |
AM0646 # 02 Y:2013 | 02 | 2013 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $42,430 | $14,500 | Not Implemented |
AM0646 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,500 | $242,900 | Not Implemented |