IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

28

matching recommendations
Reset
NAICS 33531 Electrical Equipment Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0574 # 09 Y:2005 09 2005 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $3,350 $12,520 Not Implemented
CO0574 # 08 Y:2005 08 2005 RECOVER WASTE HEAT FROM EQUIPMENT $3,410 $1,420 Not Implemented
CO0574 # 07 Y:2005 07 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,000 $41,750 Not Implemented
CO0574 # 06 Y:2005 06 2005 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING $450 $110 Not Implemented
CO0574 # 05 Y:2005 05 2005 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $162 $118 Implemented
CO0574 # 04 Y:2005 04 2005 REMOVE ROLLERS FROM THE MACHINES AND CLEAN IN A CLOSED SOLVENT CLEANER $1,170 $1,150 Not Implemented
CO0574 # 03 Y:2005 03 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,160 $210 Implemented
CO0574 # 02 Y:2005 02 2005 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $3,700 $2,350 Not Implemented
CO0574 # 01 Y:2005 01 2005 TURN OFF EQUIPMENT WHEN NOT IN USE $37,120 $6,000 Not Implemented
CO0574 # 10 Y:2005 10 2005 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $2,830 $6,160 Not Implemented
CO0574 # 11 Y:2005 11 2005 USE SOLAR HEAT TO HEAT MAKE-UP AIR $840 $6,120 Not Implemented
GT0799 # 02 Y:2005 02 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,582 $3,682 Implemented
GT0799 # 06 Y:2005 06 2005 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $16,500 $60,000 Implemented
GT0799 # 05 Y:2005 05 2005 RECOVER WASTE HEAT FROM EQUIPMENT $29,409 $260,000 Not Implemented
GT0799 # 04 Y:2005 04 2005 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $4,608 $12,000 Not Implemented
GT0799 # 03 Y:2005 03 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,040 $280,000 Not Implemented
GT0799 # 01 Y:2005 01 2005 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $6,890 $450 Not Implemented
BD0277 # 07 Y:2005 07 2005 SHUT OFF PILOTS IN STANDBY EQUIPMENT $736 $0 Implemented
BD0277 # 08 Y:2005 08 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $426 $297 Implemented
BD0277 # 09 Y:2005 09 2005 INSTALL OCCUPANCY SENSORS $395 $525 Implemented
BD0277 # 06 Y:2005 06 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,301 $800 Implemented
BD0277 # 05 Y:2005 05 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,482 $0 Implemented
BD0277 # 04 Y:2005 04 2005 RECOVER WASTE HEAT FROM EQUIPMENT $1,514 $1,200 Implemented
BD0277 # 03 Y:2005 03 2005 USE RADIANT HEATER FOR SPOT HEATING $2,870 $4,800 Implemented
BD0277 # 02 Y:2005 02 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,675 $2,008 Not Implemented