Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
37
matching recommendationsNAICS | 33531 | Electrical Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0756 # 01 Y:2022 | 01 | 2022 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $73,790 | $0 | Implemented |
OR0756 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,116 | $120,000 | Implemented |
OR0756 # 03 Y:2022 | 03 | 2022 | MODIFY CURRENT INCENTIVE PROGRAM | $978 | $0 | Not Implemented |
OR0756 # 04 Y:2022 | 04 | 2022 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $38,280 | $221,950 | Not Implemented |
DL0207 # 10 Y:2022 | 10 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,800 | $6,208 | Implemented |
DL0207 # 01 Y:2022 | 01 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,027 | $0 | Implemented |
DL0207 # 13 Y:2022 | 13 | 2022 | ELIMINATE LEAKS IN COMBUSTIBLE GAS LINES | $1,993 | $2,500 | Implemented |
DL0207 # 12 Y:2022 | 12 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $298 | $1,434 | Not Implemented |
DL0207 # 11 Y:2022 | 11 | 2022 | INSULATE BARE EQUIPMENT | $797 | $2,124 | Not Implemented |
DL0207 # 09 Y:2022 | 09 | 2022 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $2,543 | $6,428 | Not Implemented |
DL0207 # 08 Y:2022 | 08 | 2022 | USE HEAT PUMP FOR SPACE CONDITIONING | $3,608 | $4,012 | Not Implemented |
DL0207 # 07 Y:2022 | 07 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $801 | $449 | Implemented |
DL0207 # 06 Y:2022 | 06 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,522 | $1,016 | Implemented |
DL0207 # 05 Y:2022 | 05 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $557 | $1,000 | Implemented |
DL0207 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $100 | $400 | Not Implemented |
DL0207 # 03 Y:2022 | 03 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $182 | $0 | Not Implemented |
DL0207 # 02 Y:2022 | 02 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $383 | $315 | Not Implemented |
IC0260 # 01 Y:2022 | 01 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,208 | $1,715 | Not Implemented |
IC0260 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,349 | $400 | Not Implemented |
IC0260 # 05 Y:2022 | 05 | 2022 | INSTALL OCCUPANCY SENSORS | $563 | $1,190 | Not Implemented |
IC0260 # 04 Y:2022 | 04 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,800 | $0 | Not Implemented |
IC0260 # 03 Y:2022 | 03 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,387 | $3,452 | Not Implemented |
IC0260 # 02 Y:2022 | 02 | 2022 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,139 | $0 | Not Implemented |
WV0621 # 01 Y:2022 | 01 | 2022 | INSTALL OCCUPANCY SENSORS | $12,269 | $21,859 | Implemented |
WV0621 # 02 Y:2022 | 02 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $9,862 | $48,343 | Not Implemented |