Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,754
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0560 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,722 | $100 | n/a |
LE0560 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $9,378 | $9,800 | n/a |
LE0560 # 04 Y:2024 | 04 | 2024 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $2,378 | $2,500 | n/a |
LE0560 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $16,740 | $51,000 | n/a |
LE0560 # 06 Y:2024 | 06 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,350 | $11,000 | n/a |
LE0560 # 07 Y:2024 | 07 | 2024 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $9,755 | $45,000 | n/a |
OK1107 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,461 | $20,075 | n/a |
OK1107 # 02 Y:2024 | 02 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $99,540 | $804,825 | n/a |
OK1107 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $33,098 | $353,808 | n/a |
OK1107 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,761 | $0 | n/a |
OK1107 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,963 | $3,416 | n/a |
OK1107 # 06 Y:2024 | 06 | 2024 | INSTALL OCCUPANCY SENSORS | $1,278 | $792 | n/a |
OK1107 # 07 Y:2024 | 07 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $461 | $354 | n/a |
OK1107 # 08 Y:2024 | 08 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $1,517 | $1,048 | n/a |
SJ0015 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $179,675 | $962,431 | n/a |
SJ0015 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,301 | $7,684 | n/a |
SJ0015 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $676 | $680 | n/a |
SJ0015 # 04 Y:2024 | 04 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,809 | $766 | n/a |
SJ0015 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,211 | $98 | n/a |
SJ0015 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,763 | $0 | n/a |
SJ0015 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,620 | $1,986 | n/a |
SJ0015 # 08 Y:2024 | 08 | 2024 | COMBINE UTILITY METERS | $1,748 | $0 | n/a |
SJ0015 # 09 Y:2024 | 09 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $146,431 | $0 | n/a |
DL0237 # 01 Y:2024 | 01 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,341 | $0 | n/a |
DL0237 # 02 Y:2024 | 02 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,667 | $0 | n/a |