Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
145
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0356 # 03 Y:2023 | 03 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $29,176 | $63,400 | Not Implemented |
MZ0356 # 09 Y:2023 | 09 | 2023 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $10,677 | $100,000 | Not Implemented |
MZ0356 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,731 | $440 | Not Implemented |
MZ0356 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,117 | $14,802 | Implemented |
MZ0356 # 06 Y:2023 | 06 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $525,252 | $3,450,533 | Not Implemented |
MZ0356 # 05 Y:2023 | 05 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,120 | $2,680 | Implemented |
MZ0356 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $519 | $415 | Implemented |
MZ0356 # 08 Y:2023 | 08 | 2023 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $7,202 | $7,540 | Not Implemented |
MZ0356 # 07 Y:2023 | 07 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $135,000 | $306,035 | Not Implemented |
MZ0343 # 07 Y:2023 | 07 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $52,726 | $2,400 | n/a |
MZ0343 # 08 Y:2023 | 08 | 2023 | OPTIMIZE PLANT POWER FACTOR | $126,570 | $196,842 | n/a |
MZ0343 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,575 | $28,807 | n/a |
MZ0343 # 04 Y:2023 | 04 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $8,146 | $1,330 | n/a |
MZ0343 # 05 Y:2023 | 05 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,303 | $5,150 | n/a |
MZ0343 # 09 Y:2023 | 09 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $175,679 | $545,812 | n/a |
MZ0343 # 03 Y:2023 | 03 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,510 | $9,100 | n/a |
MZ0343 # 01 Y:2023 | 01 | 2023 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $4,951 | $31,059 | n/a |
MZ0343 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,711 | $360 | n/a |
MZ0306 # 03 Y:2022 | 03 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $35,350 | $30,500 | Not Implemented |
MZ0306 # 05 Y:2022 | 05 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,459 | $17,421 | Not Implemented |
MZ0306 # 06 Y:2022 | 06 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $640 | $160 | Not Implemented |
MZ0306 # 02 Y:2022 | 02 | 2022 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $4,781 | $18,650 | Not Implemented |
MZ0306 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $15,617 | $50,190 | Not Implemented |
MZ0306 # 07 Y:2022 | 07 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,283 | $9,100 | Not Implemented |
MZ0306 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $247 | $870 | Implemented |