Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
49
matching recommendationsNAICS | 3363 | Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0358 # 03 Y:2008 | 03 | 2008 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $467 | $0 | Implemented |
SF0358 # 02 Y:2008 | 02 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,229 | $150 | Not Implemented |
SF0358 # 01 Y:2008 | 01 | 2008 | REPAIR AND ELIMINATE STEAM LEAKS | $1,987 | $0 | Implemented |
LM0098 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,551 | $700 | Implemented |
LM0098 # 02 Y:2005 | 02 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $148 | $308 | Not Implemented |
LM0098 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,413 | $6,375 | Not Implemented |
LM0098 # 04 Y:2005 | 04 | 2005 | INSTALL SENSORS TO DETECT DEFECTS | $94,133 | $49,500 | Implemented |
LM0098 # 05 Y:2005 | 05 | 2005 | DEVELOP STANDARD OPERATING PROCEDURES | $216,000 | $11,800 | Implemented |
LM0098 # 06 Y:2005 | 06 | 2005 | MOVE PRODUCT USING MECHANICAL MEANS | $30,000 | $20,000 | Not Implemented |
LM0098 # 07 Y:2005 | 07 | 2005 | INSTALL AUTOMATIC PACKING EQUIPMENT | $27,000 | $50,000 | Not Implemented |
SF0261 # 04 Y:2003 | 04 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $26,010 | $33,679 | Not Implemented |
SF0261 # 01 Y:2003 | 01 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $10,012 | $0 | Implemented |
SF0261 # 02 Y:2003 | 02 | 2003 | UPGRADE CONTROLS ON COMPRESSORS | $3,924 | $52 | Not Implemented |
SF0261 # 03 Y:2003 | 03 | 2003 | INSTALL OCCUPANCY SENSORS | $4,341 | $485 | Not Implemented |
SF0261 # 05 Y:2003 | 05 | 2003 | BURN WOOD BY-PRODUCTS FOR HEAT | $25,467 | $4,500 | Implemented |
SF0261 # 06 Y:2003 | 06 | 2003 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $63,661 | $36,750 | Not Implemented |
SF0242 # 04 Y:2002 | 04 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,397 | $3,036 | Not Implemented |
SF0242 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,642 | $300 | Implemented |
SF0242 # 02 Y:2002 | 02 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,176 | $572 | Implemented |
SF0242 # 03 Y:2002 | 03 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,518 | $1,217 | Implemented |
SF0242 # 08 Y:2002 | 08 | 2002 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $16,216 | $16,216 | Not Implemented |
SF0242 # 07 Y:2002 | 07 | 2002 | USE PHOTOCELL CONTROLS | $433 | $1,200 | Not Implemented |
SF0242 # 06 Y:2002 | 06 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,020 | $3,067 | Not Implemented |
SF0242 # 05 Y:2002 | 05 | 2002 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $553 | $1,000 | Not Implemented |